1520 S CARDIFF AVE 90035

Certificate Information: 1520 S CARDIFF AVE 90035

Application / Permit
20014-10002-01299
Plan Check / Job No.
B21LA03903
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL TO 20014-10000-01299. TO REVISE WORK DESCRIPTION TO READ: "NEW SINGLE FAMILY DWELLING WITH ATTACHED GARAGE". REVISE STRUCTURAL INVENTORY TO REFLECT NEW BUILDING IN LIEU OF ADDITION.
Permit Issued
Issued on 3/10/2021
Issuing Office
Current Status
Permit Finaled on 8/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Issued 3/10/2021 APPLICANT
Building Plans Picked Up 3/12/2021 APPLICANT
Permit Finaled 8/25/2022 OGANES TARAKHCHYAN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Drexel Construction Management Llc; Lic. No.: 1014160-B 5168 W PICO BLVD      LOS ANGELES, CA 90019
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 3/19/2021 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 3/19/2021 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 4/9/2021 Partial Approval KEVIN SARGSYAN
METHANE-Barrier 4/9/2021 Approved KEVIN SARGSYAN
METHANE-Subgrade 4/9/2021 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 4/29/2021 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 6/9/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 6/18/2021 Corrections Issued KEVIN SARGSYAN
METHANE-Rough 6/18/2021 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 6/18/2021 Corrections Issued KEVIN SARGSYAN
Verify Sprinkler Sign Off 6/18/2021 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/21/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 6/21/2021 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/23/2021 Not Ready for Inspection KEVIN SARGSYAN
Insulation 6/23/2021 Partial Approval KEVIN SARGSYAN
Sewer 8/17/2021 Partial Approval KEVIN SARGSYAN
Sewer 8/19/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 10/15/2021 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 10/15/2021 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 11/3/2021 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 11/3/2021 Partial Approval KEVIN SARGSYAN
METHANE-Rough 11/3/2021 Corrections Issued KEVIN SARGSYAN
Verify Sprinkler Sign Off 11/3/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 11/8/2021 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 8/25/2022 Approved OGANES TARAKHCHYAN
Drywall Nailing 8/25/2022 Approved OGANES TARAKHCHYAN
Final 8/25/2022 Permit Finaled OGANES TARAKHCHYAN
METHANE-Final 8/25/2022 Approved OGANES TARAKHCHYAN
METHANE-Rough 8/25/2022 Approved OGANES TARAKHCHYAN
Service/Power Release 8/25/2022 Approved OGANES TARAKHCHYAN