7365 N HILLSVIEW CT 91307

Certificate Information: 7365 N HILLSVIEW CT 91307

Application / Permit
20014-10002-00990
Plan Check / Job No.
B20LA23839
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FIRST AND SECOND FLOOR ADDITION TO EXISTING SFD SUPPLEMENTAL PERMIT TO 20014-20000-00990
Permit Issued
Issued on 6/8/2021
Issuing Office
Current Status
Permit Finaled on 3/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2020 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 CRYSTEL MAALOUF
Corrections Issued 2/4/2021 CRYSTEL MAALOUF
Quality Review Completed 2/25/2021 WING SUEN
Applicant returned to address corrections 5/14/2021 CRYSTEL MAALOUF
Plan Check Approved 6/3/2021 CRYSTEL MAALOUF
Issued 6/8/2021 APPLICANT
Permit Finaled 3/2/2022 STEVEN BACK

Permit Application Clearance Information

ZA Case Cleared 4/20/2021 NOAH MCCOY
Eng Process Fee Ord 176,300 Cleared 4/26/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 5/10/2021 LEE GUILBEAUX
GPI Written Notices Cleared 5/14/2021 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 5/14/2021 CRYSTEL MAALOUF
Hydrant and Access approval Cleared 5/24/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Liu,, Joseph; Lic. No.: C60045 825 S GOLDEN WEST AVE 9      ARCADIA, CA 91007

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/2/2021 Corrections Issued DAVID STEPANYAN
Footing/Foundation/Slab 7/9/2021 Approved DAVID STEPANYAN
Deputy Reinf. Concrete 7/13/2021 No Access for Inspection DAVID STEPANYAN
Deputy Wood Construction 1/6/2022 Conditional Approval MORRIS JACKSON
Deputy Wood Construction 2/2/2022 Conditional Approval JESUS PINEDA