136 N HOBART BLVD 90004

Certificate Information: 136 N HOBART BLVD 90004

Application / Permit
20014-10001-05621
Plan Check / Job No.
B21LA17188
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL TO 20014-10000-05621 . CHANGE OF SCOPE TO NEW ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
Permit Issued
Issued on 3/4/2022
Issuing Office
Current Status
Permit Finaled on 3/17/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/14/2021 APPLICANT
Assigned to Plan Check Engineer 9/17/2021 RACHEL BEYENE
Corrections Issued 9/24/2021 RACHEL BEYENE
Plan Check Approved 2/4/2022 DANIEL SANJUAN
Issued 3/4/2022 APPLICANT
Building Plans Picked Up 3/18/2022 APPLICANT
Permit Finaled 3/16/2023 JEFFREY MEAD

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/20/2021 WALLIE JONG
Sewer availability Cleared 12/20/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/27/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/21/2022 Conditional Approval SHAVONNE ESPINOZA
PLUMBING-Rough 5/23/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Excavation/Setback/Form/Re-Bar 6/8/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Excavation/Setback/Form/Re-Bar 6/13/2022 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 6/17/2022 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 6/17/2022 Approved JOSEPH MCGARRY
Special/Order Compliance 6/17/2022 Corrections Issued JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 7/1/2022 Approved JEFFREY MEAD
Gas Test 7/1/2022 Approved JEFFREY MEAD
Sewer 7/1/2022 Approved JEFFREY MEAD
BUILDING-Rough-Frame 10/17/2022 Approved JEFFREY MEAD
ELECTRICAL-Rough 10/17/2022 Approved JEFFREY MEAD
Green Building Rough 10/17/2022 Approved JEFFREY MEAD
HVAC-Rough 10/17/2022 Approved JEFFREY MEAD
Interior/Exterior Lathing 10/17/2022 Partial Approval JEFFREY MEAD
PLUMBING-Rough 10/17/2022 Corrections Issued JEFFREY MEAD
Insulation 10/31/2022 Approved JEFFREY MEAD
Shower Pan 10/31/2022 Approved JEFFREY MEAD
Drywall Nailing 11/10/2022 Approved JEFFREY MEAD
Final 3/7/2023 Corrections Issued JEFFREY MEAD
Footing/Foundation/Slab 3/7/2023 Approved JEFFREY MEAD
Green Building Final 3/7/2023 Approved JEFFREY MEAD
PLUMBING-Final 3/7/2023 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Approved JEFFREY MEAD
Smoke Detectors 3/7/2023 Approved JEFFREY MEAD
ELECTRICAL-Final 3/16/2023 Approved JEFFREY MEAD
Final 3/16/2023 Permit Finaled JEFFREY MEAD
HVAC-Final 3/16/2023 Approved JEFFREY MEAD
PLUMBING-Final 3/16/2023 Approved JEFFREY MEAD