4169 S BRIGHTON AVE 90062
Certificate Information: 4169 S BRIGHTON AVE 90062
- Application / Permit
- 20014-10001-04569
- Plan Check / Job No.
- B23LA02034
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL TO PERMIT #20014-10000-04569 TO REVISE THE SCOPE OF WORK TO "NEW CONSTRUCTION OF DETACHED 1-STORY ADU" PER ORDINANCE
- Permit Issued
- Issued on 9/13/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | VICTOR CHEN |
| Corrections Issued | 2/21/2023 | VICTOR CHEN |
| Building Plans Picked Up | 2/22/2023 | APPLICANT |
| Applicant returned to address corrections | 5/16/2023 | LUKE GONZALES |
| Plan Check Approved | 9/13/2023 | LUKE GONZALES |
| Issued | 9/13/2023 | APPLICANT |
| Permit Finaled | 9/26/2024 | SABAS ALONSO |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/27/2023 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2023 | JESSICA OPINION |
Contact Information
| Contractor | Lua'S Construction Inc; Lic. No.: 760513-B | 689 TIMBER BAY LANE BEAUMONT, CA 92223 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 10/4/2023 | Partial Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 10/13/2023 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 10/25/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/11/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 9/11/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 9/11/2024 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 9/11/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 9/11/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 9/11/2024 | Approved | SABAS ALONSO |
| Service/Power Release | 9/11/2024 | Not Ready for Inspection | SABAS ALONSO |
| Verify Sprinkler Sign Off | 9/11/2024 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/26/2024 | Approved | SABAS ALONSO |
| Final | 9/26/2024 | Permit Finaled | SABAS ALONSO |
| HVAC-Final | 9/26/2024 | Approved | SABAS ALONSO |
| Service/Power Release | 9/26/2024 | Approved | SABAS ALONSO |