4169 S BRIGHTON AVE 90062

Certificate Information: 4169 S BRIGHTON AVE 90062

Application / Permit
20014-10001-04569
Plan Check / Job No.
B23LA02034
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL TO PERMIT #20014-10000-04569 TO REVISE THE SCOPE OF WORK TO "NEW CONSTRUCTION OF DETACHED 1-STORY ADU" PER ORDINANCE
Permit Issued
Issued on 9/13/2023
Issuing Office
Metro
Current Status
Permit Finaled on 9/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 VICTOR CHEN
Corrections Issued 2/21/2023 VICTOR CHEN
Building Plans Picked Up 2/22/2023 APPLICANT
Applicant returned to address corrections 5/16/2023 LUKE GONZALES
Plan Check Approved 9/13/2023 LUKE GONZALES
Issued 9/13/2023 APPLICANT
Permit Finaled 9/26/2024 SABAS ALONSO

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/27/2023 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 6/27/2023 JESSICA OPINION

Contact Information

Contractor Lua'S Construction Inc; Lic. No.: 760513-B 689 TIMBER BAY LANE      BEAUMONT, CA 92223
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 10/4/2023 Partial Inspection SABAS ALONSO
Footing/Foundation/Slab 10/13/2023 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 10/25/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 9/11/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 9/11/2024 Not Ready for Inspection SABAS ALONSO
Final 9/11/2024 Not Ready for Inspection SABAS ALONSO
Green Building Final 9/11/2024 Approved SABAS ALONSO
Green Building Rough 9/11/2024 Approved SABAS ALONSO
PLUMBING-Final 9/11/2024 Approved SABAS ALONSO
Service/Power Release 9/11/2024 Not Ready for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 9/11/2024 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 9/26/2024 Approved SABAS ALONSO
Final 9/26/2024 Permit Finaled SABAS ALONSO
HVAC-Final 9/26/2024 Approved SABAS ALONSO
Service/Power Release 9/26/2024 Approved SABAS ALONSO