5655 N LOUISE AVE 91316
Certificate Information: 5655 N LOUISE AVE 91316
- Application / Permit
- 20014-10001-04431
- Plan Check / Job No.
- B21LA02647
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL PERMIT TO 20014-10000-04431 TO REVISE SCOPE OF WORK FROM ADDITION AND CONVERSION OF EXISTING STORAGE TO NEW DETACHED ADU. STORAGE DEMO'D UNDER SEPARATE PERMIT
- Permit Issued
- Issued on 5/25/2021
- Issuing Office
- Current Status
- Permit Finaled on 1/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2021 | ADAM HEGAZI |
| Corrections Issued | 3/22/2021 | ADAM HEGAZI |
| Plan Check Approved | 5/25/2021 | ADAM HEGAZI |
| Issued | 5/25/2021 | APPLICANT |
| Building Plans Picked Up | 6/16/2021 | APPLICANT |
| Permit Finaled-Status Void | 11/19/2021 | SEAN HAUPT |
| Re-Activate Permit | 12/17/2021 | SEAN HAUPT |
| Permit Finaled | 1/5/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 5/10/2021 | SUNG JOON WON |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2021 | ABDULLAH SADOZAI |
| Roof/Waste drainage to street | Cleared | 5/18/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/1/2021 | Corrections Issued | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 6/1/2021 | Conditional Approval | STEVEN BACK |
| Footing/Foundation/Slab | 6/1/2021 | Approved | STEVEN BACK |
| PLUMBING-Rough | 6/1/2021 | Partial Approval | STEVEN BACK |
| Deputy Wood Construction | 6/17/2021 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 6/23/2021 | Approved | STEVEN BACK |
| Gas Test | 6/23/2021 | Partial Approval | STEVEN BACK |
| HVAC-Rough | 6/23/2021 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 6/23/2021 | Approved | STEVEN BACK |
| Shower Pan | 6/23/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 6/24/2021 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 6/29/2021 | Approved | STEVEN BACK |
| Green Building Rough | 6/29/2021 | Approved | STEVEN BACK |
| Insulation | 6/29/2021 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 6/29/2021 | Approved | STEVEN BACK |
| MERV13>=Rough | 6/29/2021 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 6/29/2021 | Approved | STEVEN BACK |
| Insulation | 7/2/2021 | Corrections Issued | STEPHANIE SWANSON |
| Underground Mechanical | 7/12/2021 | Partial Approval | STEVEN BACK |
| Drywall Nailing | 7/19/2021 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 10/8/2021 | Not Ready for Inspection | STEVEN BACK |
| Final | 10/8/2021 | Corrections Issued | STEVEN BACK |
| Green Building Final | 10/8/2021 | Approved | STEVEN BACK |
| MERV13>=Final | 10/8/2021 | Approved | STEVEN BACK |
| PLUMBING-Final | 10/8/2021 | Approved | STEVEN BACK |
| Service/Power Release | 10/8/2021 | Not Ready for Inspection | STEVEN BACK |
| Smoke Detectors | 10/8/2021 | Not Ready for Inspection | STEVEN BACK |
| Final | 10/26/2021 | Not Ready for Inspection | SEAN HAUPT |
| Service/Power Release | 10/26/2021 | Corrections Issued | SEAN HAUPT |
| Smoke Detectors | 10/26/2021 | Approved | SEAN HAUPT |
| Final | 11/9/2021 | Not Ready for Inspection | SEAN HAUPT |
| Service/Power Release | 11/9/2021 | Not Ready for Inspection | SEAN HAUPT |
| Final | 11/19/2021 | Conditional Approval | SEAN HAUPT |
| Service/Power Release | 11/19/2021 | Approved | SEAN HAUPT |