320 N GOWER ST 90004

Certificate Information: 320 N GOWER ST 90004

Application / Permit
20014-10001-04259
Plan Check / Job No.
B21LA19246
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL PERMIT TO 20014-10000-04259 TO REVISE ARCHITECT OF RECORD AND ENGINEER OF RECORD. REVISE FLOOR PLAN OF SFD WITH CHANGES TO STRUCTURAL DRAWINGS.
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
Permit Finaled on 2/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2021 APPLICANT
Assigned to Plan Check Engineer 11/9/2021 CRYSTEL MAALOUF
Corrections Issued 11/19/2021 CRYSTEL MAALOUF
Quality Review Completed 11/29/2021 KEN GILL
Plan Check Approved 2/23/2022 CRYSTEL MAALOUF
Issued 3/2/2022 APPLICANT
Building Plans Picked Up 3/11/2022 APPLICANT
Permit Finaled 2/15/2023 ALIZAH MAYAGOITIA

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Goliath Construction; Lic. No.: 1056541-B 6914 RADFORD AVE      NORTH HOLLYWOOD, CA 91605
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/24/2022 Corrections Issued SHAVONNE ESPINOZA
ELECTRICAL-Rough 3/31/2022 Partial Inspection SHAVONNE ESPINOZA
Footing/Foundation/Slab 3/31/2022 Corrections Issued SHAVONNE ESPINOZA
Footing/Foundation/Slab 4/4/2022 Conditional Approval SHAVONNE ESPINOZA
HVAC-Rough 4/29/2022 Partial Approval SHAVONNE ESPINOZA
PLUMBING-Rough 4/29/2022 Corrections Issued SHAVONNE ESPINOZA
ELECTRICAL-Rough 5/4/2022 Corrections Issued SHAVONNE ESPINOZA
PLUMBING-Rough 5/4/2022 Approved SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/6/2022 Approved SHAVONNE ESPINOZA
Wood Frame 5/11/2022 Corrections Issued SHAVONNE ESPINOZA
BUILDING-Rough-Frame 5/19/2022 Not Ready for Inspection SHAVONNE ESPINOZA
METHANE-Rough 5/19/2022 Approved SHAVONNE ESPINOZA
Wood Frame 5/19/2022 Approved SHAVONNE ESPINOZA
ELECTRICAL-Rough 5/26/2022 Approved SHAVONNE ESPINOZA
Interior/Exterior Lathing 5/26/2022 Corrections Issued SHAVONNE ESPINOZA
ELECTRICAL-Rough 6/1/2022 Approved SHAVONNE ESPINOZA
HVAC-Rough 6/1/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Insulation 6/7/2022 Approved SHAVONNE ESPINOZA
Interior/Exterior Lathing 6/7/2022 Approved SHAVONNE ESPINOZA
Drywall Nailing 7/8/2022 Approved JEFFREY MEAD
Interior/Exterior Lathing 7/8/2022 Approved JEFFREY MEAD
Shower Pan 7/8/2022 Approved JEFFREY MEAD
BUILDING-Rough-Frame 2/15/2023 Approved ALIZAH MAYAGOITIA
Final 2/15/2023 Permit Finaled ALIZAH MAYAGOITIA
Smoke Detectors 2/15/2023 Approved ALIZAH MAYAGOITIA