2301 W 76TH ST 90043
Certificate Information: 2301 W 76TH ST 90043
- Application / Permit
- 20014-10001-04116
- Plan Check / Job No.
- B21LA13266
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL PERMIT #20014-10000-04116 TO ENLARGE ADDITION & REVISE FLOOR & STRUCTURAL DESIGN ON (E) TWO STORY SFD
- Permit Issued
- Issued on 9/21/2021
- Issuing Office
- Current Status
- Issued on 9/21/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | ZAW HAN |
| Corrections Issued | 7/26/2021 | ZAW HAN |
| Applicant returned to address corrections | 8/24/2021 | ZAW HAN |
| Applicant returned to address corrections | 9/7/2021 | ZAW HAN |
| Plan Check Approved | 9/8/2021 | ZAW HAN |
| Building Plans Picked Up | 9/15/2021 | APPLICANT |
| Issued | 9/21/2021 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/30/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gu,, Xuedong; Lic. No.: S6707 | 6560 E ESTRADA ANAHEIM, CA 92807 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/23/2021 | Corrections Issued | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 9/28/2021 | Approved | FREDDIE RIVERA |
| Insulation | 11/16/2021 | Order to Comply Issued | FREDDIE RIVERA |
| Wood Frame | 11/16/2021 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/12/2022 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 1/12/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/1/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 2/1/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 2/1/2022 | Approved | FREDDIE RIVERA |
| Insulation | 2/11/2022 | Corrections Issued | SABAS ALONSO |
| Insulation | 2/24/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/24/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Shower Pan | 2/24/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Drywall Nailing | 5/3/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 5/3/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/3/2022 | Approved | ENRIQUE MIRELES |