5761-5763 W 74TH ST 90045
Certificate Information: 5761-5763 W 74TH ST 90045
- Application / Permit
- 20014-10001-02423
- Plan Check / Job No.
- B26LA02229
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO PEMRIT 20014-10000-02423 TO REVISE THE FLOOR PLAN AND CHANGE THE WORK DESCRIPTION TO "PATIO AND JUNIOR ACCESSORY DWELLING UNIT ADDITION TO (E) SINGLE FAMILY DWELLING PER GC 66323(a)(1) and 66333."
- Permit Issued
- Issued on 3/3/2026
- Issuing Office
- Metro
- Current Status
- Issued on 3/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/22/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/22/2026 | DANIEL YIP |
| Corrections Issued | 1/22/2026 | DANIEL YIP |
| Issued | 3/3/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/18/2026 | ABEL CASILLAS |
| Sewer availability | Cleared | 2/18/2026 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2026 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/7/2026 | Approved | ANDREW BEELI |
| Deputy Drilled-In Anchors | 4/14/2026 | Conditional Approval | ANDREW BEELI |
| Footing/Foundation/Slab | 4/15/2026 | Approved | ANDREW BEELI |
| Insulation | 5/5/2026 | Corrections Issued | ANDREW BEELI |
| Wood Frame | 5/5/2026 | Not Ready for Inspection | ANDREW BEELI |
| Insulation | 5/14/2026 | Not Ready for Inspection | ANDREW BEELI |
| Special/Order Compliance | 5/29/2026 | Approved | ANDREW BEELI |
| Drywall Nailing | 6/3/2026 | Approved | ANDREW BEELI |
| Insulation | 6/3/2026 | Approved | ANDREW BEELI |