4244 N PERLITA AVE 90039

Certificate Information: 4244 N PERLITA AVE 90039

Application / Permit
20014-10001-02296
Plan Check / Job No.
B23LA05817
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental to 20014-10000-02296 to recheck lost plans. Redesign the building from the approved plans to reduce floor area, revise structural, and revise attached garage to carport.
Permit Issued
Issued on 9/18/2024
Issuing Office
Metro
Current Status
Permit Finaled on 2/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2023 APPLICANT
Assigned to Plan Check Engineer 4/20/2023 CHUNG-WEN CHUANG
Corrections Issued 5/4/2023 CHUNG-WEN CHUANG
Quality Review Completed 5/8/2023 CHARLES CHANG
Building Plans Picked Up 5/15/2023 APPLICANT
Applicant returned to address corrections 2/13/2024 WEIJIAN HUANG
Applicant returned to address corrections 4/1/2024 WEIJIAN HUANG
Applicant returned to address corrections 6/24/2024 WEIJIAN HUANG
Plan Check Approved 7/8/2024 WEIJIAN HUANG
Issued 9/18/2024 APPLICANT
Permit Finaled 2/20/2026 NICHOLAS LOPEZ

Permit Application Clearance Information

Sewer availability Cleared 6/20/2023 ADRIAN SANCHEZ
ZI Cleared 7/26/2023 RYAN LY
Eng Process Fee Ord 176,300 Cleared 7/27/2023 ADRIAN SANCHEZ
Low Impact Development (LID) Cleared 9/27/2023 SHAHIN KHAZEY
Roof/Waste drainage to street Cleared 9/28/2023 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/4/2024 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 2/4/2025 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 3/24/2025 Conditional Approval NICHOLAS LOPEZ
Rough-Elec/Plmb/HVAC 6/2/2025 Conditional Approval NICHOLAS LOPEZ
Wood Frame 6/5/2025 Approved NICHOLAS LOPEZ
Insulation 6/9/2025 Approved REGINA MENDEZ
Shower Pan 6/9/2025 Approved REGINA MENDEZ
Drywall Nailing 6/16/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 6/16/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 1/29/2026 Approved NICHOLAS LOPEZ
Final 1/29/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Final 1/29/2026 Approved NICHOLAS LOPEZ
Green Building Rough 1/29/2026 Approved NICHOLAS LOPEZ
Final 2/4/2026 Corrections Issued NICHOLAS LOPEZ
Final 2/20/2026 Permit Finaled NICHOLAS LOPEZ