2250 S GUTHRIE DR 90034
Certificate Information: 2250 S GUTHRIE DR 90034
- Application / Permit
- 20014-10001-01952
- Plan Check / Job No.
- B21LA03076
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL PERMIT TO 20014-10000-01952 FOR THE REVISAL OF SCOPE OF WORK FROM "MAJOR REMODEL OF SFD, WITH A 2-STORY ADDITION" TO "NEW SFD W/ ATTACHED GARAGE (2-STORY)"
- Permit Issued
- Issued on 3/24/2021
- Issuing Office
- Current Status
- Permit Finaled on 10/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2021 | CARLOS MONTES |
| Corrections Issued | 2/22/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 3/11/2021 | CARLOS MONTES |
| Plan Check Approved | 3/24/2021 | CARLOS MONTES |
| Issued | 3/24/2021 | APPLICANT |
| Permit Finaled | 10/4/2022 | OGANES TARAKHCHYAN |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 3/17/2021 | JOHN CONNEALLY |
Contact Information
| Architect | Rabin,, Daniel H; Lic. No.: C36893 | 2323 KENILWORTH AVENUE LOS ANGELES, CA 90039 |
| Contractor | I D C S Corporation; Lic. No.: 995061-B | 485 SOUTH ROBERTSON BLVD STE 8 BEVERLY HILLS, CA 90211 |
| Engineer | Nguyen,, Tuan Minh; Lic. No.: S5883 | 5552 W 123RD PLACE HAWTHORNE, CA 90250 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/25/2021 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/26/2021 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/8/2021 | Corrections Issued | KEVIN SARGSYAN |
| METHANE-Barrier | 4/8/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 4/8/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Reinforced Masonry Frame | 4/8/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/12/2021 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/14/2022 | Approved | ANDREW NAVE |
| Final | 9/14/2022 | Partial Inspection | ANDREW NAVE |
| Footing/Foundation/Slab | 9/14/2022 | Approved | ANDREW NAVE |
| Green Building Final | 9/14/2022 | Approved | ANDREW NAVE |
| Green Building Rough | 9/14/2022 | Approved | ANDREW NAVE |
| METHANE-Barrier | 9/14/2022 | Approved | ANDREW NAVE |
| METHANE-Final | 9/14/2022 | Approved | ANDREW NAVE |
| METHANE-Rough | 9/14/2022 | Approved | ANDREW NAVE |
| METHANE-Subgrade | 9/14/2022 | Approved | ANDREW NAVE |
| Verify Sprinkler Sign Off | 9/14/2022 | Approved | ANDREW NAVE |
| Final | 10/4/2022 | Permit Finaled | OGANES TARAKHCHYAN |
| Service/Power Release | 10/4/2022 | Approved | OGANES TARAKHCHYAN |