12527 W WIXOM ST 91605
Certificate Information: 12527 W WIXOM ST 91605
- Application / Permit
- 20014-10001-01688
- Plan Check / Job No.
- B21LA01900
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMNETAL PERMIT TO 20014-20000-01688 TO REVISE THE CEILING HEIGHTS &TO REVISE THE WORK DESCRIPTION TO READ "ONE STORY ADDITION & REMODEL TO THE (E) 1-STORY SFD PER PLAN AND TO REVISE THE FOUNDATION PLAN."
- Permit Issued
- Issued on 3/4/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2021 | MAHNAZ NOURHASHEMI |
| Issued | 3/4/2021 | APPLICANT |
| Permit Finaled | 12/8/2021 | CHRISTOPHER DELLEFIELD |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/12/2021 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2021 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 3/19/2021 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 3/23/2021 | Approved | DAVID MATSON |
| Wood Frame | 4/26/2021 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2021 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2021 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 5/25/2021 | Corrections Issued | JOHN HAYES |
| Wood Frame | 6/2/2021 | Corrections Issued | JOHN HAYES |
| Wood Frame | 6/8/2021 | Corrections Issued | JOHN HAYES |
| Wood Frame | 6/14/2021 | Partial Approval | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/22/2021 | Partial Approval | JOHN HAYES |
| Insulation | 6/28/2021 | Approved | MORRIS JACKSON |
| Drywall Nailing | 7/2/2021 | Approved | JOHN HAYES |
| Final | 9/27/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 9/27/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 12/1/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 12/1/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 12/8/2021 | Permit Finaled | CHRISTOPHER DELLEFIELD |