512 W 52ND PL 90037
Certificate Information: 512 W 52ND PL 90037
- Application / Permit
- 20014-10001-00332
- Plan Check / Job No.
- B21LA21887
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL TO 20014-20000-00332, TO ADD NEW FLOOR AREA AND CHANGE DESIGN,NEW SLAB,REMOVE EXISITNG ROOF FRAMING AND REFRAME NEW ROOF, NEW FLOOR PLAN DESIGN AND TO ADD MORE SQUARE FEET AREA AND A BEDROOM.replace structural inventory
- Permit Issued
- Issued on 8/24/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 12/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 2/25/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 2/25/2022 | SAI KHUM |
| Building Plans Picked Up | 3/10/2022 | APPLICANT |
| Applicant returned to address corrections | 4/21/2023 | ARSALAN SHABESTARI |
| Plan Check Approved | 8/23/2023 | ARSALAN SHABESTARI |
| Issued | 8/24/2023 | APPLICANT |
| Permit Finaled | 12/16/2024 | DANIEL GONZALEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 7/15/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 7/15/2022 | JEANETTE VONG |
| CPC | Cleared | 8/3/2022 | MARITZA PRZEKOP |
| Construction near power lines | Cleared | 9/7/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/7/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 8/14/2023 | VICTOR MENDOZA |
Contact Information
| Contractor | Abm Construction; Lic. No.: 1071332-B | 4179 CARLOTTA ST SIMI VALLEY, CA 93063 |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/19/2023 | Partial Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 9/26/2023 | Not Ready for Inspection | JEREMY TODD |
| Footing/Foundation/Slab | 10/30/2023 | Corrections Issued | JEREMY TODD |
| Deputy Reinf. Concrete | 11/2/2023 | Partial Approval | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 11/6/2023 | Corrections Issued | JEREMY TODD |
| Excavation/Setback/Form/Re-Bar | 11/7/2023 | Corrections Issued | JEREMY TODD |
| Footing/Foundation/Slab | 12/13/2023 | Not Ready for Inspection | JEREMY TODD |
| Footing/Foundation/Slab | 12/18/2023 | Not Ready for Inspection | JEREMY TODD |
| Excavation/Setback/Form/Re-Bar | 1/25/2024 | Partial Approval | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 1/31/2024 | Corrections Issued | JEREMY TODD |
| Footing/Foundation/Slab | 2/2/2024 | Not Ready for Inspection | JEREMY TODD |
| Footing/Foundation/Slab | 2/12/2024 | Approved | JEREMY TODD |
| Deputy Wood Construction | 3/27/2024 | No Access for Inspection | DANIEL GUEVARA |
| Deputy Drilled-In Anchors | 3/28/2024 | Approved | DANIEL GONZALEZ |
| Deputy Wood Construction | 3/28/2024 | Approved | DANIEL GONZALEZ |
| Wood Frame | 3/28/2024 | Not Ready for Inspection | DANIEL GONZALEZ |
| BUILDING-Rough-Frame | 4/16/2024 | Corrections Issued | DANIEL GONZALEZ |
| ELECTRICAL-Rough | 4/16/2024 | Not Ready for Inspection | DANIEL GONZALEZ |
| HVAC-Rough | 4/16/2024 | Corrections Issued | DANIEL GONZALEZ |
| PLUMBING-Rough | 4/16/2024 | Corrections Issued | DANIEL GONZALEZ |
| BUILDING-Rough-Frame | 4/19/2024 | Approved | DANIEL GONZALEZ |
| ELECTRICAL-Rough | 4/19/2024 | Approved | DANIEL GONZALEZ |
| MERV13>=Rough | 4/19/2024 | Approved | DANIEL GONZALEZ |
| PLUMBING-Rough | 4/19/2024 | Approved | DANIEL GONZALEZ |
| Insulation | 5/6/2024 | Approved | DANIEL GONZALEZ |
| Interior/Exterior Lathing | 5/6/2024 | Partial Approval | DANIEL GONZALEZ |
| Underground Mechanical | 5/6/2024 | Partial Approval | DANIEL GONZALEZ |
| Drywall Nailing | 5/20/2024 | Approved | DANIEL GUEVARA |
| Shower Pan | 5/20/2024 | Approved | DANIEL GUEVARA |
| Interior/Exterior Lathing | 5/24/2024 | Corrections Issued | DANIEL GUEVARA |
| Interior/Exterior Lathing | 6/7/2024 | Approved | DANIEL GONZALEZ |
| Service/Power Release | 8/14/2024 | Corrections Issued | DANIEL GONZALEZ |
| Service/Power Release | 8/19/2024 | Approved | DANIEL GONZALEZ |
| Final | 11/13/2024 | Corrections Issued | DANIEL GONZALEZ |
| Smoke Detectors | 11/13/2024 | Approved | DANIEL GONZALEZ |
| Final | 12/3/2024 | Not Ready for Inspection | DANIEL GONZALEZ |
| MERV13>=Final | 12/3/2024 | Not Ready for Inspection | DANIEL GONZALEZ |
| Final | 12/16/2024 | Permit Finaled | DANIEL GONZALEZ |
| MERV13>=Final | 12/16/2024 | Approved | DANIEL GONZALEZ |