9104 S WILTON PL 90047
Certificate Information: 9104 S WILTON PL 90047
- Application / Permit
- 20014-10000-05839
- Plan Check / Job No.
- B20LA24322
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) DETACHED GARAGE AND ADDITION TO BECOME (N) ADU PRE ORDINANCE, LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 6/9/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2021 | AUNG SOE |
| Corrections Issued | 4/5/2021 | AUNG SOE |
| Plan Check Approved | 11/22/2021 | FERNANDO FLORES |
| Building Plans Picked Up | 12/3/2021 | APPLICANT |
| Issued | 6/9/2022 | APPLICANT |
| CofO in Progress | 10/18/2023 | ENRIQUE MIRELES |
| CofO in Progress | 10/18/2023 | ENRIQUE MIRELES |
| Permit Finaled | 10/29/2023 | DEROLD HAUFF |
| CofO Issued | 10/29/2023 | DEROLD HAUFF |
| Permit Finaled | 10/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 8/10/2021 | STEVE MELGAR |
| Construction near power lines | Cleared | 9/29/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 10/6/2021 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 11/8/2021 | STEVE MELGAR |
Contact Information
| Contractor | A New Look Custom; Lic. No.: 926176-B | 8940 DALTON AVE LOS ANGELES, CA 90047 |
| Engineer | Lopez,, Mauricio Jose; Lic. No.: C36801 | 1391 N THIRD AVE UPLAND, CA 91786 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/14/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Barrier | 7/14/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Subgrade | 7/14/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/4/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/1/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/1/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2022 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 11/1/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Insulation | 11/1/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| METHANE-Rough | 11/1/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/1/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/16/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 11/16/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 11/16/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 12/20/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/30/2022 | Corrections Issued | ENRIQUE MIRELES |
| Final | 8/18/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 8/18/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/18/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 8/18/2023 | Approved | ENRIQUE MIRELES |
| Final | 10/17/2023 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 10/17/2023 | Approved | ENRIQUE MIRELES |