9104 S WILTON PL 90047

Certificate Information: 9104 S WILTON PL 90047

Application / Permit
20014-10000-05839
Plan Check / Job No.
B20LA24322
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF (E) DETACHED GARAGE AND ADDITION TO BECOME (N) ADU PRE ORDINANCE, LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 6/9/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/27/2021 APPLICANT
Assigned to Plan Check Engineer 3/30/2021 AUNG SOE
Corrections Issued 4/5/2021 AUNG SOE
Plan Check Approved 11/22/2021 FERNANDO FLORES
Building Plans Picked Up 12/3/2021 APPLICANT
Issued 6/9/2022 APPLICANT
CofO in Progress 10/18/2023 ENRIQUE MIRELES
CofO in Progress 10/18/2023 ENRIQUE MIRELES
Permit Finaled 10/29/2023 DEROLD HAUFF
CofO Issued 10/29/2023 DEROLD HAUFF
Permit Finaled 10/29/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/6/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/10/2021 STEVE MELGAR
Sewer availability Cleared 8/10/2021 STEVE MELGAR
Construction near power lines Cleared 9/29/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 10/6/2021 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 11/8/2021 STEVE MELGAR

Contact Information

Contractor A New Look Custom; Lic. No.: 926176-B 8940 DALTON AVE      LOS ANGELES, CA 90047
Engineer Lopez,, Mauricio Jose; Lic. No.: C36801 1391 N THIRD AVE      UPLAND, CA 91786

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/14/2022 Approved ENRIQUE MIRELES
METHANE-Barrier 7/14/2022 Approved ENRIQUE MIRELES
METHANE-Subgrade 7/14/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 8/4/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/1/2022 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 11/1/2022 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 11/1/2022 Corrections Issued ENRIQUE MIRELES
Green Building Rough 11/1/2022 Not Ready for Inspection ENRIQUE MIRELES
Insulation 11/1/2022 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Rough 11/1/2022 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 11/1/2022 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 11/16/2022 Approved ENRIQUE MIRELES
Green Building Rough 11/16/2022 Approved ENRIQUE MIRELES
METHANE-Rough 11/16/2022 Approved ENRIQUE MIRELES
Drywall Nailing 12/20/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 12/30/2022 Corrections Issued ENRIQUE MIRELES
Final 8/18/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 8/18/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/18/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 8/18/2023 Approved ENRIQUE MIRELES
Final 10/17/2023 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 10/17/2023 Approved ENRIQUE MIRELES