5931 W 76TH ST 90045

Certificate Information: 5931 W 76TH ST 90045

Application / Permit
20014-10000-05823
Plan Check / Job No.
B20LA24287
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT EXISTING GARAGE INTO ADU, AND ADDITION TO THE EXISTING GARAGE TO BE PORTION OF THE NEW ADU
Permit Issued
Issued on 3/5/2021
Issuing Office
Current Status
CofO Issued on 9/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2021 APPLICANT
Assigned to Plan Check Engineer 1/4/2021 LARRY LEE
Corrections Issued 1/4/2021 LARRY LEE
Applicant returned to address corrections 2/3/2021 MONICA RAMIREZ
Plan Check Approved 2/25/2021 MONICA RAMIREZ
Issued 3/5/2021 APPLICANT
CofO in Progress 9/1/2021 BRENDAN LOONEY
Permit Finaled 9/21/2021 DANIEL ORRANTE
CofO Issued 9/21/2021 DANIEL ORRANTE
Permit Finaled 9/21/2021 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/5/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 1/5/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/6/2021 DINAH GARIN
Sewer availability Cleared 1/6/2021 DINAH GARIN
Grading Pre-Inspection Cleared 1/11/2021 BARTON HOLMES
Specific Plan Cleared 1/14/2021 PEDRO AYALA

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C91866 7157 ALVERN ST   G306    LOS ANGELES, CA

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/23/2021 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Rough 4/23/2021 Not Ready for Inspection JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/23/2021 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/23/2021 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 4/23/2021 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 4/23/2021 Not Ready for Inspection JUAN VALENZUELA
Wood Frame 4/23/2021 Not Ready for Inspection JUAN VALENZUELA
Deputy Drilled-In Anchors 4/28/2021 Conditional Approval BRENDAN LOONEY
Footing/Foundation/Slab 5/20/2021 Not Ready for Inspection BRENDAN LOONEY
Deputy Drilled-In Anchors 6/7/2021 No Access for Inspection AMY COLIN
Footing/Foundation/Slab 6/9/2021 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 6/25/2021 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 6/25/2021 Corrections Issued BRENDAN LOONEY
HVAC-Rough 6/25/2021 Approved BRENDAN LOONEY
PLUMBING-Rough 6/25/2021 Corrections Issued BRENDAN LOONEY
Rough-Elec/Plmb/HVAC 6/25/2021 Not Ready for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 7/1/2021 Approved BRENDAN LOONEY
ELECTRICAL-Rough 7/1/2021 Approved BRENDAN LOONEY
HVAC-Rough 7/1/2021 Approved BRENDAN LOONEY
PLUMBING-Rough 7/1/2021 Approved BRENDAN LOONEY
Rough-Elec/Plmb/HVAC 7/1/2021 Approved BRENDAN LOONEY
Deputy Wood Construction 7/13/2021 Conditional Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 7/16/2021 Approved BRENDAN LOONEY
Insulation 7/16/2021 Approved BRENDAN LOONEY
Drywall Nailing 7/28/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 7/28/2021 Conditional Approval BRENDAN LOONEY
ELECTRICAL-Final 8/31/2021 Approved BRENDAN LOONEY
Final 8/31/2021 OK to Issue CofO BRENDAN LOONEY
HVAC-Final 8/31/2021 Approved BRENDAN LOONEY
PLUMBING-Final 8/31/2021 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 8/31/2021 SGSOV Approved BRENDAN LOONEY
Smoke Detectors 8/31/2021 Approved BRENDAN LOONEY