15719 W STARE ST 91343
Certificate Information: 15719 W STARE ST 91343
- Application / Permit
- 20014-10000-05810
- Plan Check / Job No.
- B20LA24218
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- (N) 23'10" X 21'-10" RECREATIONAL ROOM ADDITION WITH HALF BATH , TO AN (E) DETACHED GARAGE.
- Permit Issued
- Issued on 5/3/2021
- Issuing Office
- Current Status
- CofO Issued on 7/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2021 | STANLEY RAAP |
| Corrections Issued | 1/9/2021 | STANLEY RAAP |
| Building Plans Picked Up | 1/14/2021 | APPLICANT |
| Plan Check Approved | 5/3/2021 | CRISTINA SALAZAR |
| Issued | 5/3/2021 | APPLICANT |
| CofO in Progress | 7/26/2022 | JAVIER RAMOS JR |
| Permit Finaled | 7/29/2022 | DANIEL ORRANTE |
| CofO Issued | 7/29/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/29/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2021 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 4/25/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 4/26/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/6/2021 | Approved | MARK JOHNSON |
| Underground Mechanical | 7/6/2021 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 3/21/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Partial Approval | JAVIER RAMOS JR |
| Green Building Rough | 3/21/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| MERV13>=Rough | 3/21/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Rough-Elec/Plmb/HVAC | 3/21/2022 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/29/2022 | Partial Approval | JAVIER RAMOS JR |
| Green Building Rough | 3/29/2022 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Rough | 3/29/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| MERV13>=Rough | 3/29/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 3/29/2022 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 3/29/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/5/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 4/5/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 4/5/2022 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 4/5/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 4/5/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/5/2022 | Approved | JAVIER RAMOS JR |
| MERV13>=Rough | 4/5/2022 | Partial Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/8/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 4/8/2022 | Approved | JAVIER RAMOS JR |
| MERV13>=Rough | 4/8/2022 | Approved | JAVIER RAMOS JR |
| Final | 5/12/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 5/12/2022 | Approved | RAUL OLAGI |
| MERV13>=Final | 5/12/2022 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 5/12/2022 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 5/12/2022 | Approved | RAUL OLAGI |
| Final | 5/19/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| MERV13>=Final | 5/19/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 5/19/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Final | 5/26/2022 | Conditional Approval | JAVIER RAMOS JR |
| MERV13>=Final | 5/26/2022 | Approved | JAVIER RAMOS JR |