15719 W STARE ST 91343

Certificate Information: 15719 W STARE ST 91343

Application / Permit
20014-10000-05810
Plan Check / Job No.
B20LA24218
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
(N) 23'10" X 21'-10" RECREATIONAL ROOM ADDITION WITH HALF BATH , TO AN (E) DETACHED GARAGE.
Permit Issued
Issued on 5/3/2021
Issuing Office
Current Status
CofO Issued on 7/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2021 APPLICANT
Assigned to Plan Check Engineer 1/5/2021 STANLEY RAAP
Corrections Issued 1/9/2021 STANLEY RAAP
Building Plans Picked Up 1/14/2021 APPLICANT
Plan Check Approved 5/3/2021 CRISTINA SALAZAR
Issued 5/3/2021 APPLICANT
CofO in Progress 7/26/2022 JAVIER RAMOS JR
Permit Finaled 7/29/2022 DANIEL ORRANTE
CofO Issued 7/29/2022 DANIEL ORRANTE
Permit Finaled 7/29/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/20/2021 GUILLERMO PETRA
Low Impact Development Cleared 4/25/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 4/26/2021 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/6/2021 Approved MARK JOHNSON
Underground Mechanical 7/6/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 3/21/2022 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/21/2022 Partial Approval JAVIER RAMOS JR
Green Building Rough 3/21/2022 Not Ready for Inspection JAVIER RAMOS JR
MERV13>=Rough 3/21/2022 Not Ready for Inspection JAVIER RAMOS JR
Rough-Elec/Plmb/HVAC 3/21/2022 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 3/29/2022 Partial Approval JAVIER RAMOS JR
Green Building Rough 3/29/2022 Partial Approval JAVIER RAMOS JR
HVAC-Rough 3/29/2022 Not Ready for Inspection JAVIER RAMOS JR
MERV13>=Rough 3/29/2022 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 3/29/2022 Approved JAVIER RAMOS JR
Underground Mechanical 3/29/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 4/5/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 4/5/2022 Approved JAVIER RAMOS JR
Green Building Rough 4/5/2022 Approved JAVIER RAMOS JR
HVAC-Rough 4/5/2022 Approved JAVIER RAMOS JR
Insulation 4/5/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 4/5/2022 Approved JAVIER RAMOS JR
MERV13>=Rough 4/5/2022 Partial Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 4/8/2022 Approved JAVIER RAMOS JR
Drywall Nailing 4/8/2022 Approved JAVIER RAMOS JR
MERV13>=Rough 4/8/2022 Approved JAVIER RAMOS JR
Final 5/12/2022 Corrections Issued RAUL OLAGI
Green Building Final 5/12/2022 Approved RAUL OLAGI
MERV13>=Final 5/12/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/12/2022 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 5/12/2022 Approved RAUL OLAGI
Final 5/19/2022 Not Ready for Inspection JAVIER RAMOS JR
MERV13>=Final 5/19/2022 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/19/2022 SGSOV Approved JAVIER RAMOS JR
Final 5/26/2022 Conditional Approval JAVIER RAMOS JR
MERV13>=Final 5/26/2022 Approved JAVIER RAMOS JR