15951 W CHATSWORTH ST 91344

Certificate Information: 15951 W CHATSWORTH ST 91344

Application / Permit
20014-10000-05779
Plan Check / Job No.
B20LA24139
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**eplan** CONVERT (E) GARAGE (1954VN80164) TO ADU AND ADDITION PER LAMC 12.22 A.33(c) AND (d) AND PER WFPP
Permit Issued
Issued on 6/2/2021
Issuing Office
Current Status
CofO Issued on 12/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2020 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 CRYSTEL MAALOUF
Corrections Issued 2/5/2021 CRYSTEL MAALOUF
Quality Review Completed 2/5/2021 HERNAN ARREOLA
Applicant returned to address corrections 3/19/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 3/25/2021 CRYSTEL MAALOUF
Plan Check Approved 4/14/2021 CRYSTEL MAALOUF
Issued 6/2/2021 APPLICANT
CofO in Progress 12/20/2021 MICHAEL TEMPLE
CofO Issued 12/29/2021 MICHAEL SMITH
Permit Finaled 12/29/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/8/2021 GABRIEL ROBLES
Permit Cleared 2/8/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 2/8/2021 GABRIEL ROBLES
Sewer availability Cleared 2/16/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 2/17/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 3/19/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/16/2021 Approved MARK JOHNSON
Excavation/Setback/Form/Re-Bar 7/20/2021 Approved DAVID SCANTLIN
Sewer 7/20/2021 Approved DAVID SCANTLIN
ELECTRICAL-Rough 7/28/2021 Partial Approval MARK JOHNSON
Underground Mechanical 7/28/2021 Approved MARK JOHNSON
ELECTRICAL-Rough 8/20/2021 Approved MARK JOHNSON
HVAC-Rough 8/20/2021 Corrections Issued MARK JOHNSON
PLUMBING-Rough 8/20/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 8/24/2021 Partial Approval MARK JOHNSON
Green Building Rough 8/24/2021 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 8/24/2021 Approved MARK JOHNSON
MERV13>=Rough 8/24/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 9/1/2021 Approved MARK JOHNSON
ELECTRICAL-Rough 9/1/2021 Corrections Issued MARK JOHNSON
Green Building Rough 9/1/2021 Approved MARK JOHNSON
Insulation 9/1/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 9/1/2021 Approved MARK JOHNSON
Shower Pan 9/8/2021 Approved ADAM ESCOTO
Drywall Nailing 9/13/2021 Approved ADAM ESCOTO
ELECTRICAL-Final 11/18/2021 Corrections Issued MICHAEL TEMPLE
Final 11/18/2021 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 11/18/2021 Approved MICHAEL TEMPLE
Green Building Final 11/18/2021 Not Ready for Inspection MICHAEL TEMPLE
HVAC-Final 11/18/2021 Not Ready for Inspection MICHAEL TEMPLE
MERV13>=Final 11/18/2021 Not Ready for Inspection MICHAEL TEMPLE
PLUMBING-Final 11/18/2021 Approved MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 11/18/2021 SGSOV Approved MICHAEL TEMPLE
Smoke Detectors 11/18/2021 Approved MICHAEL TEMPLE
Final 12/21/2021 OK to Issue CofO MICHAEL TEMPLE
Green Building Final 12/21/2021 Approved MICHAEL TEMPLE
MERV13>=Final 12/21/2021 Approved MICHAEL TEMPLE