15951 W CHATSWORTH ST 91344
Certificate Information: 15951 W CHATSWORTH ST 91344
- Application / Permit
- 20014-10000-05779
- Plan Check / Job No.
- B20LA24139
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **eplan** CONVERT (E) GARAGE (1954VN80164) TO ADU AND ADDITION PER LAMC 12.22 A.33(c) AND (d) AND PER WFPP
- Permit Issued
- Issued on 6/2/2021
- Issuing Office
- Current Status
- CofO Issued on 12/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 2/5/2021 | CRYSTEL MAALOUF |
| Quality Review Completed | 2/5/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 3/19/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 3/25/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 4/14/2021 | CRYSTEL MAALOUF |
| Issued | 6/2/2021 | APPLICANT |
| CofO in Progress | 12/20/2021 | MICHAEL TEMPLE |
| CofO Issued | 12/29/2021 | MICHAEL SMITH |
| Permit Finaled | 12/29/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/8/2021 | GABRIEL ROBLES |
| Permit | Cleared | 2/8/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 2/8/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 2/16/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 3/19/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/16/2021 | Approved | MARK JOHNSON |
| Excavation/Setback/Form/Re-Bar | 7/20/2021 | Approved | DAVID SCANTLIN |
| Sewer | 7/20/2021 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 7/28/2021 | Partial Approval | MARK JOHNSON |
| Underground Mechanical | 7/28/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 8/20/2021 | Approved | MARK JOHNSON |
| HVAC-Rough | 8/20/2021 | Corrections Issued | MARK JOHNSON |
| PLUMBING-Rough | 8/20/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 8/24/2021 | Partial Approval | MARK JOHNSON |
| Green Building Rough | 8/24/2021 | Not Ready for Inspection | MARK JOHNSON |
| HVAC-Rough | 8/24/2021 | Approved | MARK JOHNSON |
| MERV13>=Rough | 8/24/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 9/1/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 9/1/2021 | Corrections Issued | MARK JOHNSON |
| Green Building Rough | 9/1/2021 | Approved | MARK JOHNSON |
| Insulation | 9/1/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 9/1/2021 | Approved | MARK JOHNSON |
| Shower Pan | 9/8/2021 | Approved | ADAM ESCOTO |
| Drywall Nailing | 9/13/2021 | Approved | ADAM ESCOTO |
| ELECTRICAL-Final | 11/18/2021 | Corrections Issued | MICHAEL TEMPLE |
| Final | 11/18/2021 | Corrections Issued | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 11/18/2021 | Approved | MICHAEL TEMPLE |
| Green Building Final | 11/18/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| HVAC-Final | 11/18/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| MERV13>=Final | 11/18/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| PLUMBING-Final | 11/18/2021 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 11/18/2021 | SGSOV Approved | MICHAEL TEMPLE |
| Smoke Detectors | 11/18/2021 | Approved | MICHAEL TEMPLE |
| Final | 12/21/2021 | OK to Issue CofO | MICHAEL TEMPLE |
| Green Building Final | 12/21/2021 | Approved | MICHAEL TEMPLE |
| MERV13>=Final | 12/21/2021 | Approved | MICHAEL TEMPLE |