4448 S DAWES AVE 90230
Certificate Information: 4448 S DAWES AVE 90230
- Application / Permit
- 20014-10000-05771
- Plan Check / Job No.
- B20LA24092
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR ADDITION TO REAR OF (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 7/19/2021
- Issuing Office
- Current Status
- CofO Issued on 8/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | LAMAR DAVIS |
| Corrections Issued | 2/2/2021 | LAMAR DAVIS |
| Quality Review Completed | 2/2/2021 | GARO TELMI |
| Applicant returned to address corrections | 6/4/2021 | LAMAR DAVIS |
| Plan Check Approved | 7/16/2021 | LAMAR DAVIS |
| No Progress | 7/16/2021 | LAMAR DAVIS |
| Plan Check Approved | 7/16/2021 | LAMAR DAVIS |
| Issued | 7/19/2021 | APPLICANT |
| Building Plans Picked Up | 7/22/2021 | APPLICANT |
| CofO in Progress | 8/9/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 8/15/2023 | DANIEL ORRANTE |
| CofO Issued | 8/15/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/15/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 2/16/2021 | JOE LUCKEY |
| Specific Plan | Cleared | 2/23/2021 | VALERIA CEJA |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 3/8/2021 | HISASHI KOBAYAKAWA |
| Low Impact Development | Cleared | 5/12/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/1/2021 | HISASHI KOBAYAKAWA |
Contact Information
| Architect | Hamilton,, John Patrick; Lic. No.: C28865 | 12240 VENICE BLVD SUITE 25 LOS ANGELES, CA 90066 |
| Contractor | Substrata Inc; Lic. No.: 1050826-B | 222 N PACIFIC COAST HWY SUITE 2000 EL SEGUNDO, CA 90245 |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/6/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/2/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2021 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/5/2022 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2022 | Corrections Issued | EVAN COOPER |
| HVAC-Rough | 1/5/2022 | Corrections Issued | EVAN COOPER |
| Wood Frame | 2/2/2022 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 2/9/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 2/9/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 2/9/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 2/9/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 2/9/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 3/1/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 3/17/2022 | Corrections Issued | PATRICK QUALEY |
| Drywall Nailing | 3/31/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Drywall Nailing | 4/5/2022 | Approved | RYAN SALAZAR |
| Shower Pan | 4/27/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/9/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 2/13/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 2/16/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/16/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Sewer | 2/16/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 2/16/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 2/17/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 2/22/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 2/22/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 2/23/2023 | Conditional Approval | HERBERT GIRON |
| Final | 2/23/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 2/23/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 8/9/2023 | Approved | JESUS RODRIGUEZ |
| Final | 8/9/2023 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 8/9/2023 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 8/9/2023 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 8/9/2023 | Approved | JESUS RODRIGUEZ |