9247 S HARVARD BLVD 90047

Certificate Information: 9247 S HARVARD BLVD 90047

Application / Permit
20014-10000-05770
Plan Check / Job No.
B20LA24091
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 27'6" X 39'2", 1081sf. ADDITION TO REAR (E) DWELLING.
Permit Issued
Issued on 9/15/2021
Issuing Office
Current Status
CofO Issued on 2/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2020 APPLICANT
Assigned to Plan Check Engineer 1/5/2021 STANLEY RAAP
Corrections Issued 1/9/2021 STANLEY RAAP
Applicant returned to address corrections 5/19/2021 CRISTINA SALAZAR
Applicant returned to address corrections 8/19/2021 SAMUEL GONZALEZ
Plan Check Approved 9/14/2021 DANIEL SANJUAN
Issued 9/15/2021 APPLICANT
Building Plans Picked Up 9/16/2021 APPLICANT
CofO in Progress 2/3/2025 MICHAEL LEWIS
Permit Finaled 2/11/2025 DEROLD HAUFF
CofO Issued 2/11/2025 DEROLD HAUFF
Permit Finaled 2/11/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/12/2021 THOMAS LANG
Low Impact Development Cleared 8/8/2021 TA ANH
Roof/Waste drainage to street Cleared 8/9/2021 JEANIE LAM
Sewer availability Cleared 8/10/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/4/2021 Conditional Approval FREDDIE RIVERA
METHANE-Barrier 11/4/2021 Approved FREDDIE RIVERA
METHANE-Subgrade 11/4/2021 Approved FREDDIE RIVERA
Special/Order Compliance 11/4/2021 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 12/27/2021 Corrections Issued HORACE FULTZ
PLUMBING-Rough 1/4/2022 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 1/14/2022 Partial Inspection FREDDIE RIVERA
Insulation 1/14/2022 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 12/29/2022 Partial Approval HORACE FULTZ
Green Building Rough 12/29/2022 Not Ready for Inspection HORACE FULTZ
METHANE-Rough 12/29/2022 Approved HORACE FULTZ
Deputy Wood Construction 6/28/2023 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 6/28/2023 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 7/21/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 7/27/2023 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 8/11/2023 Approved ENRIQUE MIRELES
Green Building Rough 8/11/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Final 10/10/2024 Corrections Issued AMIR NAZARIAN
Drywall Nailing 10/30/2024 No Access for Inspection AMIR NAZARIAN
Final 10/30/2024 No Access for Inspection AMIR NAZARIAN
Footing/Foundation/Slab 10/30/2024 Not Ready for Inspection AMIR NAZARIAN
Green Building Final 10/30/2024 No Access for Inspection AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 10/30/2024 SGSOV Not Ready AMIR NAZARIAN
Smoke Detectors 10/30/2024 No Access for Inspection AMIR NAZARIAN
Drywall Nailing 11/5/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 11/5/2024 Approved MICHAEL LEWIS
Final 11/14/2024 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 11/14/2024 Approved MICHAEL LEWIS
Green Building Final 11/14/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 11/14/2024 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 11/14/2024 Approved MICHAEL LEWIS
Final 11/22/2024 Corrections Issued JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 11/22/2024 SGSOV Approved JOSE MACIAS
Final 1/31/2025 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 1/31/2025 Approved MICHAEL LEWIS