9247 S HARVARD BLVD 90047
Certificate Information: 9247 S HARVARD BLVD 90047
- Application / Permit
- 20014-10000-05770
- Plan Check / Job No.
- B20LA24091
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 27'6" X 39'2", 1081sf. ADDITION TO REAR (E) DWELLING.
- Permit Issued
- Issued on 9/15/2021
- Issuing Office
- Current Status
- CofO Issued on 2/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2021 | STANLEY RAAP |
| Corrections Issued | 1/9/2021 | STANLEY RAAP |
| Applicant returned to address corrections | 5/19/2021 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 8/19/2021 | SAMUEL GONZALEZ |
| Plan Check Approved | 9/14/2021 | DANIEL SANJUAN |
| Issued | 9/15/2021 | APPLICANT |
| Building Plans Picked Up | 9/16/2021 | APPLICANT |
| CofO in Progress | 2/3/2025 | MICHAEL LEWIS |
| Permit Finaled | 2/11/2025 | DEROLD HAUFF |
| CofO Issued | 2/11/2025 | DEROLD HAUFF |
| Permit Finaled | 2/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2021 | THOMAS LANG |
| Low Impact Development | Cleared | 8/8/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 8/9/2021 | JEANIE LAM |
| Sewer availability | Cleared | 8/10/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/4/2021 | Conditional Approval | FREDDIE RIVERA |
| METHANE-Barrier | 11/4/2021 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 11/4/2021 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 11/4/2021 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 12/27/2021 | Corrections Issued | HORACE FULTZ |
| PLUMBING-Rough | 1/4/2022 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/14/2022 | Partial Inspection | FREDDIE RIVERA |
| Insulation | 1/14/2022 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2022 | Partial Approval | HORACE FULTZ |
| Green Building Rough | 12/29/2022 | Not Ready for Inspection | HORACE FULTZ |
| METHANE-Rough | 12/29/2022 | Approved | HORACE FULTZ |
| Deputy Wood Construction | 6/28/2023 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 6/28/2023 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/21/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/27/2023 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/11/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 8/11/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 10/10/2024 | Corrections Issued | AMIR NAZARIAN |
| Drywall Nailing | 10/30/2024 | No Access for Inspection | AMIR NAZARIAN |
| Final | 10/30/2024 | No Access for Inspection | AMIR NAZARIAN |
| Footing/Foundation/Slab | 10/30/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Green Building Final | 10/30/2024 | No Access for Inspection | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 10/30/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Smoke Detectors | 10/30/2024 | No Access for Inspection | AMIR NAZARIAN |
| Drywall Nailing | 11/5/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 11/5/2024 | Approved | MICHAEL LEWIS |
| Final | 11/14/2024 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 11/14/2024 | Approved | MICHAEL LEWIS |
| Green Building Final | 11/14/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 11/14/2024 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 11/14/2024 | Approved | MICHAEL LEWIS |
| Final | 11/22/2024 | Corrections Issued | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 11/22/2024 | SGSOV Approved | JOSE MACIAS |
| Final | 1/31/2025 | OK to Issue CofO | MICHAEL LEWIS |
| Service/Power Release | 1/31/2025 | Approved | MICHAEL LEWIS |