17839 W ELKWOOD ST 91335
Certificate Information: 17839 W ELKWOOD ST 91335
- Application / Permit
- 20014-10000-05769
- Plan Check / Job No.
- B20LA24085
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 2 CAR GARAGE INTO ACCESSORY DWELLING UNIT WITH AN ADDITION per LAMC 12.22.A.33(C)and(D)
- Permit Issued
- Issued on 4/9/2021
- Issuing Office
- Current Status
- CofO Issued on 7/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 1/5/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 2/23/2021 | LUKE GONZALES |
| Building Plans Picked Up | 3/9/2021 | APPLICANT |
| Plan Check Approved | 4/7/2021 | VU NGUYEN |
| Issued | 4/9/2021 | APPLICANT |
| CofO in Progress | 7/21/2021 | VINCENT HANLEY |
| Permit Finaled | 7/26/2021 | JOHN JANSON |
| CofO Issued | 7/26/2021 | JOHN JANSON |
| Permit Finaled | 7/26/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/12/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 1/12/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 1/12/2021 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 2/2/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 2/12/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Pcmr Construction Inc; Lic. No.: 1031442-B | 8942 WOODMAN AVE STE D7 ARLETA, CA 91331 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/5/2021 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 5/6/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 5/6/2021 | Partial Approval | VINCENT HANLEY |
| Sewer | 5/12/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/24/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 5/24/2021 | Approved | VINCENT HANLEY |
| Wood Frame | 5/24/2021 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2021 | Approved | VINCENT HANLEY |
| HVAC-Rough | 5/28/2021 | Approved | VINCENT HANLEY |
| Underground Mechanical | 5/28/2021 | Approved | VINCENT HANLEY |
| Insulation | 6/9/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 6/9/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 6/15/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/15/2021 | Approved | VINCENT HANLEY |
| Insulation | 6/15/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/21/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 6/21/2021 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 6/21/2021 | Approved | VINCENT HANLEY |
| Green Building Final | 6/21/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/21/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/21/2021 | SGSOV Not Ready | VINCENT HANLEY |
| Smoke Detectors | 6/21/2021 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Final | 7/13/2021 | Corrections Issued | VINCENT HANLEY |
| Final | 7/13/2021 | Corrections Issued | VINCENT HANLEY |
| Gas Test | 7/13/2021 | Approved | VINCENT HANLEY |
| Green Building Final | 7/13/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/13/2021 | SGSOV Not Ready | VINCENT HANLEY |
| Smoke Detectors | 7/13/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 7/21/2021 | Approved | VINCENT HANLEY |
| Final | 7/21/2021 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 7/21/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 7/21/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/21/2021 | SGSOV Approved | VINCENT HANLEY |