10645 W OTSEGO ST 91601
Certificate Information: 10645 W OTSEGO ST 91601
- Application / Permit
- 20014-10000-05767
- Plan Check / Job No.
- B20LA24077
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing garage to Accessory Dwelling Unit per LAMC 12.22 A.33(c) and (d) with one-story, ground floor addition
- Permit Issued
- Issued on 4/9/2021
- Issuing Office
- Current Status
- CofO Issued on 3/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2021 | RAMA DABADGE |
| Corrections Issued | 2/17/2021 | RAMA DABADGE |
| Plan Check Approved | 4/8/2021 | VU NGUYEN |
| Issued | 4/9/2021 | APPLICANT |
| CofO in Progress | 2/11/2022 | MISAEL ESPARZA |
| Permit Finaled | 3/7/2022 | MICHAEL SMITH |
| CofO Issued | 3/7/2022 | MICHAEL SMITH |
| Permit Finaled | 3/7/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/22/2021 | ADRIAN CASTRO |
| Address approval | Cleared | 2/22/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 2/22/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/25/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Azarbin,, Hamid Reza; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/5/2021 | Partial Approval | DANIEL DREW |
| Footing/Foundation/Slab | 5/18/2021 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 6/4/2021 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 7/20/2021 | Approved | DANIEL DREW |
| Footing/Foundation/Slab | 7/20/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2021 | Approved | DANIEL DREW |
| Underground Mechanical | 9/10/2021 | Not Ready for Inspection | DANIEL DREW |
| Underground Mechanical | 9/20/2021 | Not Ready for Inspection | DANIEL DREW |
| BUILDING-Rough-Frame | 9/21/2021 | No Access for Inspection | DANIEL DREW |
| Gas Test | 9/21/2021 | No Access for Inspection | DANIEL DREW |
| Green Building Rough | 9/21/2021 | No Access for Inspection | DANIEL DREW |
| Rough-Elec/Plmb/HVAC | 9/21/2021 | No Access for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 9/22/2021 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 9/22/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 9/22/2021 | Partial Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/27/2021 | Not Ready for Inspection | DANIEL DREW |
| Green Building Rough | 9/27/2021 | Not Ready for Inspection | DANIEL DREW |
| HVAC-Rough | 9/27/2021 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Rough | 9/27/2021 | Not Ready for Inspection | DANIEL DREW |
| Underground Mechanical | 9/27/2021 | Approved | DANIEL DREW |
| Sewer | 9/29/2021 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2021 | Approved | DANIEL DREW |
| HVAC-Rough | 10/4/2021 | Approved | ARAM AVEDISIAN |
| Insulation | 10/12/2021 | Corrections Issued | WILLIAM KUEHN |
| Interior/Exterior Lathing | 10/12/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Insulation | 10/19/2021 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 10/19/2021 | Partial Approval | ASHLEY THOMPSON |
| Shower Pan | 10/19/2021 | Not Ready for Inspection | ASHLEY THOMPSON |
| Drywall Nailing | 11/1/2021 | Approved | CALEB MEISTER |
| Green Building Rough | 11/1/2021 | Approved | CALEB MEISTER |
| Shower Pan | 11/3/2021 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 11/10/2021 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 11/10/2021 | Approved | DANIEL DREW |
| Shower Pan | 11/10/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 11/29/2021 | Partial Approval | ARAM AVEDISIAN |
| Final | 1/21/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 1/21/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/21/2022 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 1/21/2022 | Corrections Issued | MISAEL ESPARZA |
| Final | 1/31/2022 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 1/31/2022 | Approved | ARAM AVEDISIAN |
| Final | 2/4/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 2/4/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 2/4/2022 | SGSOV Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 2/10/2022 | Approved | MISAEL ESPARZA |
| Final | 2/10/2022 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 2/10/2022 | Approved | MISAEL ESPARZA |
| HVAC-Final | 2/10/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 2/10/2022 | Approved | MISAEL ESPARZA |