10645 W OTSEGO ST 91601

Certificate Information: 10645 W OTSEGO ST 91601

Application / Permit
20014-10000-05767
Plan Check / Job No.
B20LA24077
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing garage to Accessory Dwelling Unit per LAMC 12.22 A.33(c) and (d) with one-story, ground floor addition
Permit Issued
Issued on 4/9/2021
Issuing Office
Current Status
CofO Issued on 3/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2021 APPLICANT
Assigned to Plan Check Engineer 2/8/2021 RAMA DABADGE
Corrections Issued 2/17/2021 RAMA DABADGE
Plan Check Approved 4/8/2021 VU NGUYEN
Issued 4/9/2021 APPLICANT
CofO in Progress 2/11/2022 MISAEL ESPARZA
Permit Finaled 3/7/2022 MICHAEL SMITH
CofO Issued 3/7/2022 MICHAEL SMITH
Permit Finaled 3/7/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/22/2021 ADRIAN CASTRO
Address approval Cleared 2/22/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 2/22/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 2/24/2021 ADRIAN CASTRO
Sewer availability Cleared 2/25/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Azarbin,, Hamid Reza; Lic. No.: C64515 22655 COVELLO ST      WEST HILLS, CA 91307

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/5/2021 Partial Approval DANIEL DREW
Footing/Foundation/Slab 5/18/2021 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 6/4/2021 Corrections Issued THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 7/20/2021 Approved DANIEL DREW
Footing/Foundation/Slab 7/20/2021 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 7/29/2021 Approved DANIEL DREW
Underground Mechanical 9/10/2021 Not Ready for Inspection DANIEL DREW
Underground Mechanical 9/20/2021 Not Ready for Inspection DANIEL DREW
BUILDING-Rough-Frame 9/21/2021 No Access for Inspection DANIEL DREW
Gas Test 9/21/2021 No Access for Inspection DANIEL DREW
Green Building Rough 9/21/2021 No Access for Inspection DANIEL DREW
Rough-Elec/Plmb/HVAC 9/21/2021 No Access for Inspection DANIEL DREW
ELECTRICAL-Rough 9/22/2021 Approved LILIANA PORTILLO
PLUMBING-Rough 9/22/2021 Corrections Issued ALIZAH MAYAGOITIA
Special/Order Compliance 9/22/2021 Partial Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 9/27/2021 Not Ready for Inspection DANIEL DREW
Green Building Rough 9/27/2021 Not Ready for Inspection DANIEL DREW
HVAC-Rough 9/27/2021 Not Ready for Inspection DANIEL DREW
PLUMBING-Rough 9/27/2021 Not Ready for Inspection DANIEL DREW
Underground Mechanical 9/27/2021 Approved DANIEL DREW
Sewer 9/29/2021 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/30/2021 Approved DANIEL DREW
HVAC-Rough 10/4/2021 Approved ARAM AVEDISIAN
Insulation 10/12/2021 Corrections Issued WILLIAM KUEHN
Interior/Exterior Lathing 10/12/2021 Not Ready for Inspection WILLIAM KUEHN
Insulation 10/19/2021 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 10/19/2021 Partial Approval ASHLEY THOMPSON
Shower Pan 10/19/2021 Not Ready for Inspection ASHLEY THOMPSON
Drywall Nailing 11/1/2021 Approved CALEB MEISTER
Green Building Rough 11/1/2021 Approved CALEB MEISTER
Shower Pan 11/3/2021 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 11/10/2021 Approved DANIEL DREW
Interior/Exterior Lathing 11/10/2021 Approved DANIEL DREW
Shower Pan 11/10/2021 Approved DANIEL DREW
ELECTRICAL-Rough 11/29/2021 Partial Approval ARAM AVEDISIAN
Final 1/21/2022 Corrections Issued MISAEL ESPARZA
Green Building Final 1/21/2022 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 1/21/2022 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 1/21/2022 Corrections Issued MISAEL ESPARZA
Final 1/31/2022 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 1/31/2022 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 1/31/2022 Approved ARAM AVEDISIAN
Final 2/4/2022 Corrections Issued MISAEL ESPARZA
Green Building Final 2/4/2022 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 2/4/2022 SGSOV Approved MISAEL ESPARZA
ELECTRICAL-Final 2/10/2022 Approved MISAEL ESPARZA
Final 2/10/2022 OK to Issue CofO MISAEL ESPARZA
Green Building Final 2/10/2022 Approved MISAEL ESPARZA
HVAC-Final 2/10/2022 Approved MISAEL ESPARZA
PLUMBING-Final 2/10/2022 Approved MISAEL ESPARZA