15719 W STARE ST 91343

Certificate Information: 15719 W STARE ST 91343

Application / Permit
20014-10000-05749
Plan Check / Job No.
B20LA23956
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION TO AN EXISTING SINGLE FAMILY RESIDENCE. NEW BEDROOM/BATHROOM AND KITCHEN REMODEL
Permit Issued
Issued on 6/24/2021
Issuing Office
Current Status
CofO Issued on 7/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2020 APPLICANT
Assigned to Plan Check Engineer 12/31/2020 FARSHAD ALIMOHAMADI
Corrections Issued 1/2/2021 FARSHAD ALIMOHAMADI
Building Plans Picked Up 1/12/2021 APPLICANT
Plan Check Approved 5/10/2021 RAHEL BEYENE
Issued 6/24/2021 APPLICANT
CofO in Progress 7/26/2022 JAVIER RAMOS JR
Permit Finaled 7/29/2022 DANIEL ORRANTE
CofO Issued 7/29/2022 DANIEL ORRANTE
Permit Finaled 7/29/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/13/2021 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 4/25/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 4/26/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/26/2021 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/12/2021 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 7/12/2021 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 7/15/2021 Approved MARK JOHNSON
Underground Mechanical 7/15/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 8/26/2021 Corrections Issued MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 8/26/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 10/18/2021 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 10/18/2021 Not Ready for Inspection MARK JOHNSON
Green Building Rough 10/18/2021 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 10/18/2021 Not Ready for Inspection MARK JOHNSON
MERV13>=Rough 10/18/2021 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 10/18/2021 Not Ready for Inspection MARK JOHNSON
Rough-Elec/Plmb/HVAC 10/26/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 10/29/2021 Approved MARK JOHNSON
Green Building Rough 10/29/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 10/29/2021 Approved MARK JOHNSON
MERV13>=Rough 10/29/2021 Approved MARK JOHNSON
Shower Pan 10/29/2021 Approved MARK JOHNSON
Insulation 11/2/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 11/2/2021 Approved MARK JOHNSON
Drywall Nailing 11/8/2021 Approved MICHAEL TEMPLE
Final 5/12/2022 Corrections Issued RAUL OLAGI
Green Building Final 5/12/2022 Approved RAUL OLAGI
MERV13>=Final 5/12/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/12/2022 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 5/12/2022 Approved RAUL OLAGI
Final 5/19/2022 Not Ready for Inspection JAVIER RAMOS JR
MERV13>=Final 5/19/2022 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/19/2022 SGSOV Approved JAVIER RAMOS JR
Final 5/26/2022 Conditional Approval JAVIER RAMOS JR
MERV13>=Final 5/26/2022 Approved JAVIER RAMOS JR