1245 N HOOVER ST 90029

Certificate Information: 1245 N HOOVER ST 90029

Application / Permit
20014-10000-05724
Plan Check / Job No.
B20LA23853
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
TWO STORY ADU (815 SF) ADDITION TO EXISTING GARAGE PER 12.22 A33 C & D
Permit Issued
Issued on 4/2/2022
Issuing Office
Current Status
CofO Issued on 2/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2020 APPLICANT
Assigned to Plan Check Engineer 1/7/2021 STARR CHEN
Corrections Issued 1/9/2021 STARR CHEN
Quality Review Completed 1/15/2021 HERNAN ARREOLA
Building Plans Picked Up 1/21/2021 APPLICANT
Applicant returned to address corrections 7/2/2021 STARR CHEN
Applicant returned to address corrections 2/15/2022 STARR CHEN
Plan Check Approved 3/18/2022 STARR CHEN
Issued 4/2/2022 APPLICANT
CofO in Progress 2/25/2025 FREDDIE RIVERA
Permit Finaled 2/26/2025 DEROLD HAUFF
Permit Finaled 2/26/2025 DEROLD HAUFF
CofO Issued 2/26/2025 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 4/15/2021 RIDWAN HARDY
Grading Pre-Inspection Cleared 5/18/2021 BRIAN MILLER
Hydrant and Access approval Cleared 7/10/2021 ROBERT DUFF
Address approval Cleared 8/4/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/4/2021 JEANIE LAM
Low Impact Development Cleared 12/14/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/28/2021 THAN WIN
Sewer availability Cleared 12/30/2021 JEANIE LAM
GPI Written Notices Cleared 3/18/2022 STARR CHEN

Contact Information

Architect , ; Lic. No.: C36916       ,
Contractor D U A Build; Lic. No.: 967782-B 3579 EAST FOOTHILL BLVD #405      PASADENA, CA 91107
Engineer Garcia,, Lionel Jesus; Lic. No.: S4653 24702 NARBONNE AVE      LOMITA, CA 90717

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/8/2022 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 4/12/2022 Conditional Approval FREDDIE RIVERA
Deputy Drilled-In Anchors 4/13/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 7/13/2022 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 7/13/2022 Partial Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 7/13/2022 Partial Inspection FREDDIE RIVERA
Green Building Rough 7/13/2022 Partial Inspection FREDDIE RIVERA
HVAC-Rough 7/13/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 7/13/2022 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 7/18/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 7/18/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 7/18/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 8/3/2022 Approved STUART CHAPMAN
Green Building Rough 8/3/2022 Approved STUART CHAPMAN
Insulation 8/3/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/3/2022 Partial Approval STUART CHAPMAN
Drywall Nailing 9/8/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 9/8/2022 Approved FREDDIE RIVERA
Special/Order Compliance 11/18/2022 Corrections Issued FREDDIE RIVERA
Final 11/1/2023 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 11/1/2023 Approved FREDDIE RIVERA
Green Building Final 11/1/2023 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/1/2023 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 11/1/2023 Corrections Issued FREDDIE RIVERA
Final 10/18/2024 No Access for Inspection BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 10/18/2024 SGSOV Not Ready BRENDAN MORELLI
Smoke Detectors 10/18/2024 No Access for Inspection BRENDAN MORELLI
Final 10/22/2024 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/22/2024 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 10/22/2024 Approved FREDDIE RIVERA
Final 12/26/2024 Corrections Issued JEFFREY MEAD
ELECTRICAL-Final 12/31/2024 Approved WILLIAM SIERRA
Final 12/31/2024 Corrections Issued WILLIAM SIERRA
HVAC-Final 12/31/2024 Approved WILLIAM SIERRA
PLUMBING-Final 12/31/2024 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Final 1/27/2025 Approved FREDDIE RIVERA
Final 1/27/2025 OK to Issue CofO FREDDIE RIVERA
HVAC-Final 1/27/2025 Approved FREDDIE RIVERA
PLUMBING-Final 1/27/2025 Approved FREDDIE RIVERA