2114 S MALCOLM AVE 90025
Certificate Information: 2114 S MALCOLM AVE 90025
- Application / Permit
- 20014-10000-05716
- Plan Check / Job No.
- B20LA23787
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 2-STORY BEDROOM, BATHROOM, LAUNDRY ROOM ADDITION TO REAR OF (E) SFD. FIRST FLOOR ON ADDITION TO BE OPEN PATIO ON THREE SIDES.
- Permit Issued
- Issued on 7/15/2021
- Issuing Office
- Current Status
- CofO Issued on 9/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | LAWRENCE QUIRANTE |
| Corrections Issued | 1/2/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 3/4/2021 | SINA KHOSRAVI |
| Plan Check Approved | 5/11/2021 | RICARDO RAMIREZ |
| Building Plans Picked Up | 6/23/2021 | APPLICANT |
| Issued | 7/15/2021 | APPLICANT |
| CofO in Progress | 9/17/2022 | RICHARD STEINBACH |
| Permit Finaled | 9/22/2022 | DANIEL ORRANTE |
| CofO Issued | 9/22/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/22/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/2/2021 | PATRICK MISCHLICH |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2021 | NIKTA MOUSAVI |
| Roof/Waste drainage to street | Cleared | 3/30/2021 | NIKTA MOUSAVI |
Contact Information
| Architect | , ; Lic. No.: C35683 | 10242 PARKINSON AVE WHITTIER, CA 90605 |
| Contractor | Watson David Construction Inc; Lic. No.: 934184-B | 4457 HAZELBROOK AVENUE LONG BEACH, CA 90808 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/20/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 7/20/2021 | Partial Approval | OGANES TARAKHCHYAN |
| METHANE-Barrier | 7/20/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 7/20/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| METHANE-Barrier | 8/2/2021 | Approved | OGANES TARAKHCHYAN |
| METHANE-Final | 8/2/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| METHANE-Rough | 8/2/2021 | Approved | OGANES TARAKHCHYAN |
| Deputy Methane Barrier | 8/3/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 8/5/2021 | Approved | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 8/6/2021 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/6/2021 | Partial Approval | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 8/6/2021 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 9/30/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Other (see comments) | 9/30/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 2/4/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Rough | 2/4/2022 | Approved | OGANES TARAKHCHYAN |
| Rough-Elec/Plmb/HVAC | 2/4/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 2/4/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/9/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 2/9/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/15/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 2/15/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 2/15/2022 | Approved | OGANES TARAKHCHYAN |
| Insulation | 2/17/2022 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 2/25/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/25/2022 | Approved | STEPHANIE SWANSON |
| Shower Pan | 3/25/2022 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 3/30/2022 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 6/3/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 6/3/2022 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 6/3/2022 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 6/3/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 7/15/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 7/15/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 7/20/2022 | Approved | JOHN KIDWELL |
| HVAC-Final | 7/20/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 7/20/2022 | Approved | JOHN KIDWELL |
| Final | 7/22/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 9/7/2022 | Conditional Approval | JOHN KIDWELL |