13252 W HERRON ST 91342
Certificate Information: 13252 W HERRON ST 91342
- Application / Permit
- 20014-10000-05712
- Plan Check / Job No.
- B20LA23762
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE WITH ADDITION TO A DETACHED ADU PER ORDINANCE (2-STORY)
- Permit Issued
- Issued on 5/19/2022
- Issuing Office
- Current Status
- CofO Issued on 2/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | CARLOS MONTES |
| Corrections Issued | 4/10/2021 | CARLOS MONTES |
| Quality Review Completed | 4/20/2021 | WING SUEN |
| Applicant returned to address corrections | 1/5/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 2/10/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 3/2/2022 | CARLOS MONTES |
| Plan Check Approved | 3/22/2022 | CARLOS MONTES |
| Issued | 5/19/2022 | APPLICANT |
| CofO in Progress | 9/20/2023 | KEVIN BERBERYAN |
| Permit Finaled | 2/7/2024 | RUBEN SALAS |
| CofO Issued | 2/7/2024 | RUBEN SALAS |
| Permit Finaled | 2/7/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/5/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/6/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 1/20/2022 | ABDULLAH SADOZAI |
| Low Impact Development | Cleared | 5/19/2022 | LONDY ALVARADO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vartanian,, Albert; Lic. No.: C39989 | PO BOX 857 VERDUGO CITY, CA 91046 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/29/2022 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 8/9/2022 | Corrections Issued | ALAN MORELOS |
| Footing/Foundation/Slab | 8/16/2022 | Approved | ARAM AVEDISIAN |
| Wood Frame | 9/2/2022 | Partial Approval | ARAM AVEDISIAN |
| Wood Frame | 9/26/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| Deputy Wood Construction | 9/30/2022 | Conditional Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/14/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/14/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 11/14/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/14/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 12/6/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 12/6/2022 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 12/6/2022 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 12/22/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 12/22/2022 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 6/12/2023 | Partial Approval | MICHEL ABAJAN |
| Sewer | 6/29/2023 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 7/14/2023 | Approved | RAUL OLAGI |
| Final | 8/22/2023 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 8/22/2023 | Not Ready for Inspection | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 8/22/2023 | SGSOV Not Ready | ROBERT GOLD |
| Smoke Detectors | 8/22/2023 | Conditional Approval | ROBERT GOLD |
| ELECTRICAL-Final | 9/19/2023 | Approved | KEVIN BERBERYAN |
| Final | 9/19/2023 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 9/19/2023 | Approved | KEVIN BERBERYAN |
| HVAC-Final | 9/19/2023 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 9/19/2023 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 9/19/2023 | Approved | KEVIN BERBERYAN |