13252 W HERRON ST 91342

Certificate Information: 13252 W HERRON ST 91342

Application / Permit
20014-10000-05712
Plan Check / Job No.
B20LA23762
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE WITH ADDITION TO A DETACHED ADU PER ORDINANCE (2-STORY)
Permit Issued
Issued on 5/19/2022
Issuing Office
Current Status
CofO Issued on 2/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 CARLOS MONTES
Corrections Issued 4/10/2021 CARLOS MONTES
Quality Review Completed 4/20/2021 WING SUEN
Applicant returned to address corrections 1/5/2022 CARLOS MONTES
Applicant returned to address corrections 2/10/2022 CARLOS MONTES
Applicant returned to address corrections 3/2/2022 CARLOS MONTES
Plan Check Approved 3/22/2022 CARLOS MONTES
Issued 5/19/2022 APPLICANT
CofO in Progress 9/20/2023 KEVIN BERBERYAN
Permit Finaled 2/7/2024 RUBEN SALAS
CofO Issued 2/7/2024 RUBEN SALAS
Permit Finaled 2/7/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/5/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/6/2021 GABRIEL ROBLES
Sewer availability Cleared 5/6/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 1/20/2022 ABDULLAH SADOZAI
Low Impact Development Cleared 5/19/2022 LONDY ALVARADO

Contact Information

Contractor Owner-Builder       ,
Engineer Vartanian,, Albert; Lic. No.: C39989 PO BOX 857      VERDUGO CITY, CA 91046

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/29/2022 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 8/9/2022 Corrections Issued ALAN MORELOS
Footing/Foundation/Slab 8/16/2022 Approved ARAM AVEDISIAN
Wood Frame 9/2/2022 Partial Approval ARAM AVEDISIAN
Wood Frame 9/26/2022 Not Ready for Inspection ARAM AVEDISIAN
Deputy Wood Construction 9/30/2022 Conditional Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 11/14/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 11/14/2022 Approved ARAM AVEDISIAN
HVAC-Rough 11/14/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 11/14/2022 Approved ARAM AVEDISIAN
Insulation 12/6/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/6/2022 Partial Approval ARAM AVEDISIAN
Shower Pan 12/6/2022 Approved ARAM AVEDISIAN
Drywall Nailing 12/22/2022 Approved ARAM AVEDISIAN
Green Building Rough 12/22/2022 Approved ARAM AVEDISIAN
Underground Mechanical 6/12/2023 Partial Approval MICHEL ABAJAN
Sewer 6/29/2023 Approved ARAM AVEDISIAN
Underground Mechanical 7/14/2023 Approved RAUL OLAGI
Final 8/22/2023 Corrections Issued ROBERT GOLD
Green Building Final 8/22/2023 Not Ready for Inspection ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 8/22/2023 SGSOV Not Ready ROBERT GOLD
Smoke Detectors 8/22/2023 Conditional Approval ROBERT GOLD
ELECTRICAL-Final 9/19/2023 Approved KEVIN BERBERYAN
Final 9/19/2023 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 9/19/2023 Approved KEVIN BERBERYAN
HVAC-Final 9/19/2023 Approved KEVIN BERBERYAN
PLUMBING-Final 9/19/2023 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/19/2023 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 9/19/2023 Approved KEVIN BERBERYAN