3800 N GLENRIDGE DR 91423
Certificate Information: 3800 N GLENRIDGE DR 91423
- Application / Permit
- 20014-10000-05711
- Plan Check / Job No.
- B20LA23753
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION TO (E) SFD (1-STORY ) NEW FAU THROUGHOUT RESIDENCE
- Permit Issued
- Issued on 10/5/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2021 | CARLOS MONTES |
| Corrections Issued | 2/5/2021 | CARLOS MONTES |
| Quality Review Completed | 2/17/2021 | GARO TELMI |
| Building Plans Picked Up | 2/23/2021 | APPLICANT |
| Applicant returned to address corrections | 6/8/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 3/11/2022 | CARLOS MONTES |
| Plan Check Approved | 10/3/2022 | CARLOS MONTES |
| Issued | 10/5/2022 | APPLICANT |
| CofO in Progress | 9/13/2024 | MISAEL ESPARZA |
| CofO Issued | 9/25/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/25/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/17/2021 | OLGA AYALA |
| BHO/Hillside ordinance | Cleared | 9/7/2021 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 9/7/2021 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 9/7/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/7/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 11/23/2021 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 3/31/2022 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 8/31/2022 | ROMAN GUTIERREZ |
| BHO/Hillside ordinance | Cleared | 9/26/2022 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 10/3/2022 | VASIL MIHALEV |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ahmed,, Zafar; Lic. No.: GE2720 | 113 TOMATO SPRINGS IRVINE, CA 92618 |
| Engineer | Mutka,, Jason Richard; Lic. No.: C72255 | PO BOX 77144 CORONA, CA 92877 |
| Geologist | Aflakian,, Farzad; Lic. No.: EG2051 | 921 PENDIO IRVINE, CA 92620 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/15/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/9/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 11/9/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 11/17/2023 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 12/12/2023 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 12/12/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 12/12/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/15/2023 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Rough | 12/15/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Insulation | 12/20/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/20/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Shower Pan | 12/20/2023 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/26/2023 | Approved | MISAEL ESPARZA |
| Insulation | 12/26/2023 | Approved | MISAEL ESPARZA |
| Shower Pan | 12/26/2023 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 12/29/2023 | Approved | JUAN VALENZUELA |
| Green Building Rough | 12/29/2023 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 12/29/2023 | Partial Approval | JUAN VALENZUELA |
| Final | 4/9/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/9/2024 | Approved | MISAEL ESPARZA |
| Green Building Final | 4/9/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 4/9/2024 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 4/9/2024 | Approved | MISAEL ESPARZA |
| Final | 5/15/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 5/15/2024 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/15/2024 | SGSOV Not Ready | MISAEL ESPARZA |
| Final | 8/23/2024 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/23/2024 | SGSOV Approved | MISAEL ESPARZA |
| Final | 9/11/2024 | OK to Issue CofO | MISAEL ESPARZA |