|
Piling/Pier/Caisson
|
11/17/2023
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Piling/Pier/Caisson
|
11/20/2023
|
Partial Approval
|
DAVID BURKHEAD
|
|
Piling/Pier/Caisson
|
11/27/2023
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Deputy Grading
|
12/5/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
12/5/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Piling/Pier/Caisson
|
12/5/2023
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Deputy Grading
|
12/11/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
12/11/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Grading
|
12/12/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
12/12/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Grading
|
12/13/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
12/13/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Piling/Pier/Caisson
|
12/13/2023
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Grading
|
12/15/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
12/15/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Piling/Pier/Caisson
|
1/2/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
1/3/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
1/4/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
1/5/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
1/8/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Piling/Pier/Caisson
|
1/9/2024
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
2/15/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
2/15/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
2/15/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
3/26/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
3/26/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
3/26/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
3/28/2024
|
Partial Inspection
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
3/28/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
3/28/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
4/4/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
4/4/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
4/4/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
4/22/2024
|
Approved
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
4/22/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
4/22/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
4/22/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
4/22/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
5/6/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
5/6/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
5/24/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
5/24/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
5/24/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
5/24/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
5/24/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
6/17/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
6/17/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
6/17/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
6/17/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
7/30/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
7/30/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
7/30/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
9/16/2024
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
9/16/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
9/16/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
9/16/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
9/16/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
10/16/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
10/16/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
10/16/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
10/16/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
12/9/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
12/30/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
12/30/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
12/30/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Subgrade
|
12/30/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Piling/Pier/Caisson
|
12/30/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
1/10/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
1/10/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
1/10/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
1/10/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
1/29/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
1/29/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
1/29/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
2/28/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
2/28/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
2/28/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Special/Order Compliance
|
3/28/2025
|
Approved
|
DAVID BURKHEAD
|
|
Deputy Steel/Welding
|
4/23/2025
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
4/23/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
4/23/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
4/23/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
4/23/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Deputy Steel/Welding
|
4/28/2025
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Methane Barrier
|
5/20/2025
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Steel/Welding
|
5/20/2025
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
5/20/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
5/20/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
5/20/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Final
|
5/27/2025
|
Partial Approval
|
ALFREDO LOPEZ
|
|
Deputy Steel/Welding
|
6/16/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
6/16/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
6/16/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Subgrade
|
6/16/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
6/24/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
6/24/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
6/24/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
6/24/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Steel/Welding
|
7/3/2025
|
Conditional Approval
|
JEFFREY FULTON
|
|
Excavation/Setback/Form/Re-Bar
|
7/3/2025
|
Partial Inspection
|
JEFFREY FULTON
|
|
Footing/Foundation/Slab
|
7/3/2025
|
Partial Inspection
|
JEFFREY FULTON
|
|
METHANE-Barrier
|
7/3/2025
|
Partial Inspection
|
JEFFREY FULTON
|
|
METHANE-Subgrade
|
7/3/2025
|
Partial Inspection
|
JEFFREY FULTON
|
|
Excavation/Setback/Form/Re-Bar
|
7/30/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
8/1/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
8/1/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
8/1/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
8/1/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
8/8/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
8/8/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
8/8/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
8/8/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
8/18/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
8/18/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Subgrade
|
8/18/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
8/18/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
8/21/2025
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
8/21/2025
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
METHANE-Barrier
|
8/21/2025
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
METHANE-Subgrade
|
8/21/2025
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
Excavation/Setback/Form/Re-Bar
|
8/26/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
8/28/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
8/28/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
8/28/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
8/28/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
9/3/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Rough
|
9/15/2025
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
METHANE-Subgrade
|
9/15/2025
|
Corrections Issued
|
JOEY BUCHANAN
|
|
Light Gage Steel Frame
|
9/29/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
9/30/2025
|
Approved
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
10/2/2025
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Insulation
|
10/6/2025
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
10/16/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
10/16/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
10/16/2025
|
Conditional Approval
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
10/16/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
10/27/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
10/27/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
11/5/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
11/5/2025
|
Partial Inspection
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
11/5/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
11/5/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Special/Order Compliance
|
11/5/2025
|
Partial Approval
|
SCOTT SOBEL
|
|
Drywall Nailing
|
11/24/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
11/24/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
12/4/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
12/4/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
12/11/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
12/11/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
12/11/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Insulation
|
12/11/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
12/11/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
12/11/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
12/11/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
12/11/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
12/15/2025
|
Partial Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
12/15/2025
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
12/17/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
12/17/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
12/18/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Insulation
|
12/18/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
12/18/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
12/22/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
12/22/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
12/22/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
12/29/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
12/29/2025
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
12/29/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
12/29/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
1/9/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
1/9/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
1/14/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
1/14/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
1/22/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
1/22/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
1/23/2026
|
No Access for Inspection
|
MARTIN TAVITIAN
|
|
Footing/Foundation/Slab
|
1/23/2026
|
No Access for Inspection
|
MARTIN TAVITIAN
|
|
METHANE-Barrier
|
1/23/2026
|
No Access for Inspection
|
MARTIN TAVITIAN
|
|
METHANE-Subgrade
|
1/23/2026
|
No Access for Inspection
|
MARTIN TAVITIAN
|
|
Excavation/Setback/Form/Re-Bar
|
1/29/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
1/29/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
1/29/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
1/29/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
1/29/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
2/9/2026
|
Partial Approval
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
2/9/2026
|
Partial Approval
|
RAFAEL CORTES
|
|
Drywall Nailing
|
2/18/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
Interior/Exterior Lathing
|
2/18/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
2/18/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
Interior/Exterior Lathing
|
2/25/2026
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Light Gage Steel Frame
|
2/25/2026
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Light Gage Steel Frame
|
3/9/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
3/11/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
3/11/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
3/13/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
3/13/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
3/13/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
3/18/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
3/18/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Final
|
3/26/2026
|
Partial Inspection
|
DAVID BURKHEAD
|
|
METHANE-Rough
|
3/26/2026
|
Approved
|
DAVID BURKHEAD
|
|
Interior/Exterior Lathing
|
3/31/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
3/31/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
4/9/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
4/9/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
4/9/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
4/9/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
Interior/Exterior Lathing
|
4/10/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
4/21/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
4/21/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
4/21/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
4/23/2026
|
Partial Approval
|
MARTIN TAVITIAN
|
|
METHANE-Barrier
|
4/23/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
METHANE-Subgrade
|
4/23/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Reinforced Concrete Frame
|
4/23/2026
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Reinforced Concrete Frame
|
4/24/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Special/Order Compliance
|
4/27/2026
|
Approved
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
4/29/2026
|
Partial Approval
|
MARTIN TAVITIAN
|
|
METHANE-Barrier
|
4/29/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
METHANE-Subgrade
|
4/29/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Reinforced Concrete Frame
|
4/29/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Reinforced Concrete Frame
|
4/30/2026
|
Partial Approval
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
5/1/2026
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Footing/Foundation/Slab
|
5/5/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
5/5/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
5/5/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
5/5/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
5/6/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
5/8/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
5/8/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
5/8/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
5/8/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
5/14/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
5/14/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
5/14/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
5/19/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
5/19/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
5/19/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
5/19/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
5/22/2026
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
5/22/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
5/22/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
5/22/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
5/28/2026
|
Partial Approval
|
MARTIN TAVITIAN
|
|
METHANE-Barrier
|
5/28/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
METHANE-Subgrade
|
5/28/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Reinforced Concrete Frame
|
5/28/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Footing/Foundation/Slab
|
5/30/2026
|
Partial Approval
|
MARTIN TAVITIAN
|
|
METHANE-Barrier
|
5/30/2026
|
Partial Approval
|
MARTIN TAVITIAN
|
|
METHANE-Subgrade
|
5/30/2026
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Reinforced Concrete Frame
|
5/30/2026
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Excavation/Setback/Form/Re-Bar
|
6/2/2026
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
6/2/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
6/2/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
6/2/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Special/Order Compliance
|
6/4/2026
|
Approved
|
DAVID BURKHEAD
|
|
Special/Order Compliance
|
6/22/2026
|
Corrections Issued
|
DAVID BURKHEAD
|
|
Final
|
6/25/2026
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
6/25/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
6/25/2026
|
Approved
|
DAVID BURKHEAD
|
|
METHANE-Final
|
6/25/2026
|
Approved
|
DAVID BURKHEAD
|
|
METHANE-Rough
|
6/25/2026
|
Approved
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
6/25/2026
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Reinforced Masonry Frame
|
6/25/2026
|
Conditional Approval
|
DAVID BURKHEAD
|
|
SGSOV-Seismic Gas S/O Valve
|
6/25/2026
|
SGSOV Approved
|
DAVID BURKHEAD
|
|
Smoke Detectors
|
6/25/2026
|
Approved
|
DAVID BURKHEAD
|
|
Special/Order Compliance
|
6/30/2026
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Special/Order Compliance
|
7/2/2026
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Special/Order Compliance
|
7/6/2026
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Special/Order Compliance
|
7/7/2026
|
Approved
|
DAVID BURKHEAD
|
|
Final
|
7/8/2026
|
OK for TCO
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
7/8/2026
|
Approved
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
7/8/2026
|
Approved
|
DAVID BURKHEAD
|
|
Reinforced Masonry Frame
|
7/8/2026
|
Approved
|
DAVID BURKHEAD
|