3426 S KELTON AVE 90034
Certificate Information: 3426 S KELTON AVE 90034
- Application / Permit
- 20014-10000-05691
- Plan Check / Job No.
- B20LA23674
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION, INTERIOR AND EXTERIOR REMODEL OF EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 6/24/2021
- Issuing Office
- Current Status
- CofO Issued on 10/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | STARR CHEN |
| Corrections Issued | 1/9/2021 | STARR CHEN |
| Quality Review Completed | 1/15/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 3/8/2021 | STARR CHEN |
| Applicant returned to address corrections | 4/14/2021 | STARR CHEN |
| Plan Check Approved | 5/5/2021 | STARR CHEN |
| Issued | 6/24/2021 | APPLICANT |
| Building Plans Picked Up | 7/22/2021 | APPLICANT |
| CofO in Progress | 10/25/2023 | JESUS PINEDA |
| Permit Finaled | 10/26/2023 | DANIEL ORRANTE |
| CofO Issued | 10/26/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/26/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/12/2021 | KIRK LINKLATER |
| Specific Plan | Cleared | 3/12/2021 | EILEEN HUNT |
| GPI Written Notices | Cleared | 4/14/2021 | STARR CHEN |
| Low Impact Development | Cleared | 4/21/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 4/28/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 4/28/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2021 | ANTHONY MAINEZ |
Contact Information
| Contractor | All Star Prime Construction Services Inc; Lic. No.: 1034984-B | 123 S MESA ST SAN PEDRO, CA 90731 |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/21/2021 | Conditional Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 7/23/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 7/28/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 7/28/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2021 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/20/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 8/27/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Service/Power Release | 10/13/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Conditional Approval | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 11/30/2021 | Corrections Issued | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 2/3/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Deputy Wood Construction | 2/3/2022 | Conditional Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 2/3/2022 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 2/3/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 2/3/2022 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 2/3/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 2/10/2022 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 2/10/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 2/10/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 2/10/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 3/3/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 3/3/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 3/3/2022 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 3/11/2022 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 3/25/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 3/25/2022 | Approved | JOHNNY MIRANDA |
| Shower Pan | 3/25/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 10/14/2022 | Approved | CLAYTON GRAHAM |
| Final | 10/14/2022 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Final | 10/14/2022 | Corrections Issued | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 10/14/2022 | SGSOV Not Ready | CLAYTON GRAHAM |
| Smoke Detectors | 10/14/2022 | Approved | CLAYTON GRAHAM |
| HVAC-Final | 10/19/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 10/19/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Service/Power Release | 10/19/2022 | Approved | JESUS RODRIGUEZ |
| Final | 10/26/2022 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 10/26/2022 | Approved | JOHNNY MIRANDA |
| Green Building Final | 10/26/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 10/26/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 10/26/2022 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 10/26/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Final | 3/14/2023 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 3/14/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 5/23/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 10/25/2023 | OK to Issue CofO | JESUS PINEDA |