8020 S DUNFIELD AVE 90045
Certificate Information: 8020 S DUNFIELD AVE 90045
- Application / Permit
- 20014-10000-05645
- Plan Check / Job No.
- B20LA23508
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION AT FRONT OF (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 6/18/2021
- Issuing Office
- Current Status
- CofO Issued on 5/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | KEVIN MORALES |
| Corrections Issued | 1/19/2021 | KEVIN MORALES |
| Quality Review Completed | 1/21/2021 | EUGENE BARBEAU |
| Building Plans Picked Up | 1/29/2021 | APPLICANT |
| Applicant returned to address corrections | 3/24/2021 | KEVIN MORALES |
| Plan Check Approved | 6/16/2021 | KEVIN MORALES |
| Issued | 6/18/2021 | APPLICANT |
| CofO in Progress | 3/16/2022 | JESUS RODRIGUEZ |
| CofO Issued | 5/4/2022 | DANIEL ORRANTE |
| Permit Finaled | 5/4/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Encroachment in public way | Cleared | 4/6/2021 | DENNIS BRAGIN |
| Permit | Cleared | 4/6/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2021 | DENNIS BRAGIN |
| Specific Plan | Cleared | 4/19/2021 | KEVIN ARUCAN |
| Trees in Parkway | Cleared | 5/11/2021 | JOHN KIM |
| Low Impact Development | Cleared | 6/7/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 6/7/2021 | DENNIS BRAGIN |
Contact Information
| Contractor | Local Construction Remodeling; Lic. No.: 966738-B | 14901 TUBA STREET MISSION HILLS, CA 91345 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/19/2021 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 7/23/2021 | Approved | BRENDAN LOONEY |
| Sewer | 7/23/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2021 | Partial Approval | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 8/12/2021 | Conditional Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 8/13/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 8/17/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 8/17/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 8/19/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 8/20/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Rough | 8/20/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 8/20/2021 | Corrections Issued | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 8/27/2021 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 8/27/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 8/27/2021 | Approved | BRENDAN LOONEY |
| Deputy Wood Construction | 8/31/2021 | Conditional Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2021 | Approved | JOHNNY MIRANDA |
| Insulation | 9/1/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 9/1/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 9/2/2021 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Drywall Nailing | 9/10/2021 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 9/10/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 9/10/2021 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 9/15/2021 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 9/15/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 9/15/2021 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Final | 12/29/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 12/29/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 1/12/2022 | Approved | JOHN KAYON |
| Drywall Nailing | 3/16/2022 | Approved | JESUS RODRIGUEZ |
| Final | 3/16/2022 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 3/16/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 3/16/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 3/16/2022 | Approved | JESUS RODRIGUEZ |