8020 S DUNFIELD AVE 90045

Certificate Information: 8020 S DUNFIELD AVE 90045

Application / Permit
20014-10000-05645
Plan Check / Job No.
B20LA23508
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION AT FRONT OF (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
Permit Issued
Issued on 6/18/2021
Issuing Office
Current Status
CofO Issued on 5/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 KEVIN MORALES
Corrections Issued 1/19/2021 KEVIN MORALES
Quality Review Completed 1/21/2021 EUGENE BARBEAU
Building Plans Picked Up 1/29/2021 APPLICANT
Applicant returned to address corrections 3/24/2021 KEVIN MORALES
Plan Check Approved 6/16/2021 KEVIN MORALES
Issued 6/18/2021 APPLICANT
CofO in Progress 3/16/2022 JESUS RODRIGUEZ
CofO Issued 5/4/2022 DANIEL ORRANTE
Permit Finaled 5/4/2022 DANIEL ORRANTE

Permit Application Clearance Information

Encroachment in public way Cleared 4/6/2021 DENNIS BRAGIN
Permit Cleared 4/6/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 4/8/2021 DENNIS BRAGIN
Specific Plan Cleared 4/19/2021 KEVIN ARUCAN
Trees in Parkway Cleared 5/11/2021 JOHN KIM
Low Impact Development Cleared 6/7/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 6/7/2021 DENNIS BRAGIN

Contact Information

Contractor Local Construction Remodeling; Lic. No.: 966738-B 14901 TUBA STREET      MISSION HILLS, CA 91345
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/19/2021 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 7/23/2021 Approved BRENDAN LOONEY
Sewer 7/23/2021 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 8/10/2021 Partial Approval JOHNNY MIRANDA
Deputy Drilled-In Anchors 8/12/2021 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 8/13/2021 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 8/17/2021 Approved JOHNNY MIRANDA
PLUMBING-Rough 8/17/2021 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 8/19/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 8/20/2021 Not Ready for Inspection JOHNNY MIRANDA
Green Building Rough 8/20/2021 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 8/20/2021 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 8/27/2021 Partial Approval BRENDAN LOONEY
Green Building Rough 8/27/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 8/27/2021 Approved BRENDAN LOONEY
Deputy Wood Construction 8/31/2021 Conditional Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 9/1/2021 Approved JOHNNY MIRANDA
Insulation 9/1/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 9/1/2021 Not Ready for Inspection JOHNNY MIRANDA
Interior/Exterior Lathing 9/2/2021 Not Ready for Inspection SHAVONNE ESPINOZA
Drywall Nailing 9/10/2021 Partial Approval JOHNNY MIRANDA
Green Building Rough 9/10/2021 Not Ready for Inspection JOHNNY MIRANDA
Interior/Exterior Lathing 9/10/2021 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 9/15/2021 Approved JOHNNY MIRANDA
Green Building Rough 9/15/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 9/15/2021 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Final 12/29/2021 Approved ENRIQUE MIRELES
HVAC-Final 12/29/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 1/12/2022 Approved JOHN KAYON
Drywall Nailing 3/16/2022 Approved JESUS RODRIGUEZ
Final 3/16/2022 OK to Issue CofO JESUS RODRIGUEZ
Green Building Final 3/16/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/16/2022 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 3/16/2022 Approved JESUS RODRIGUEZ