19714 W VANOWEN ST 91306

Certificate Information: 19714 W VANOWEN ST 91306

Application / Permit
20014-10000-05633
Plan Check / Job No.
B20LA23473
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
PROPOSED TENANT IMPROVEMENT TO (E) RESTAURANT AND CHANGE OF USE PORTION OF (E) RETAIL/MARKET TO RESTAURANT AND NEW UNCOVERED OUTDOOR DINING AREA.
Permit Issued
Issued on 6/25/2021
Issuing Office
Current Status
CofO Issued on 12/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 ARMEN JIVALAGIAN
Green Plans Picked Up 1/6/2021 APPLICANT
Corrections Issued 1/7/2021 ARMEN JIVALAGIAN
Disabled Access Plans Picked Up 1/14/2021 APPLICANT
Quality Review Completed 1/15/2021 PETER KIM
Building Plans Picked Up 1/22/2021 APPLICANT
Applicant returned to address corrections 1/29/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 2/11/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 2/24/2021 ARMEN JIVALAGIAN
Plan Check Approved 5/18/2021 ARMEN JIVALAGIAN
Issued 6/25/2021 APPLICANT
CofO in Progress 12/15/2021 DANIEL VARNUM
Permit Finaled 12/23/2021 JEFFREY DURAN
CofO Issued 12/23/2021 JEFFREY DURAN
Permit Finaled 12/23/2021 JEFFREY DURAN

Permit Application Clearance Information

Green Code Cleared 12/30/2020 KHEDER ALRAZAA
Miscellaneous Cleared 2/17/2021 MINDY NGUYEN
ZA Case Cleared 2/17/2021 MINDY NGUYEN
ZI Cleared 2/17/2021 MINDY NGUYEN
Eng Process Fee Ord 176,300 Cleared 2/25/2021 LEE GUILBEAUX
Internal circulation Cleared 3/19/2021 SHEILA AHORAIAN
Sewer availability Cleared 3/23/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/23/2021 LEE GUILBEAUX
DAS Clearance Cleared 4/8/2021 ARMEN JIVALAGIAN
Food Service Establishment Cleared 4/22/2021 PAWAN VERMA
Food establishment approval Cleared 5/18/2021 LACDHS APPROVED

Contact Information

Architect Moradi, Owrang, Sheida; Lic. No.: C35621 22035 PROVIDENCIA STREET      WOODLAND HILLS, CA 91364
Contractor Rd & Ah Builders Inc; Lic. No.: 1059995-B 6409 POLLARD STREET      LOS ANGELES, CA 90042
Engineer Husain,, Shahzain; Lic. No.: C62744 1843 MONTGOMERY RD      THOUSAND OAKS, CA 91360

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 7/13/2021 No Access for Inspection DANIEL VARNUM
Wood Frame 7/13/2021 No Access for Inspection DANIEL VARNUM
Green Building Rough 7/19/2021 Not Ready for Inspection ANDREW DORSO
Wood Frame 7/19/2021 Partial Inspection ANDREW DORSO
Drywall Nailing 7/26/2021 No Access for Inspection DANNY RODRIGUEZ
Drywall Nailing 7/28/2021 Approved CAMERON CHABAN
Final 10/29/2021 Corrections Issued KENNETH ROBERTS
Green Building Final 10/29/2021 Not Ready for Inspection KENNETH ROBERTS
Green Building Rough 10/29/2021 Not Ready for Inspection KENNETH ROBERTS
SGSOV-Seismic Gas S/O Valve 10/29/2021 SGSOV Not Ready KENNETH ROBERTS
Smoke Detectors 10/29/2021 Not Ready for Inspection KENNETH ROBERTS
Wood Frame 10/29/2021 Not Ready for Inspection KENNETH ROBERTS
Final 11/3/2021 Not Ready for Inspection DANIEL VARNUM
Green Building Final 11/3/2021 Not Ready for Inspection DANIEL VARNUM
Green Building Rough 11/3/2021 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 11/3/2021 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 11/3/2021 Not Ready for Inspection DANIEL VARNUM
Wood Frame 11/3/2021 Not Ready for Inspection DANIEL VARNUM
Final 11/9/2021 Corrections Issued DANIEL VARNUM
Green Building Final 11/9/2021 Not Ready for Inspection DANIEL VARNUM
Green Building Rough 11/9/2021 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 11/9/2021 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 11/9/2021 Not Ready for Inspection DANIEL VARNUM
Wood Frame 11/9/2021 Not Ready for Inspection DANIEL VARNUM
Final 12/2/2021 Partial Inspection ANDREW DORSO
Green Building Final 12/2/2021 Approved ANDREW DORSO
Green Building Rough 12/2/2021 Approved ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 12/2/2021 SGSOV Approved ANDREW DORSO
Smoke Detectors 12/2/2021 Approved ANDREW DORSO
Wood Frame 12/2/2021 Approved ANDREW DORSO
Final 12/7/2021 Partial Approval DANIEL VARNUM