2018 S WEST BLVD 90016

Certificate Information: 2018 S WEST BLVD 90016

Application / Permit
20014-10000-05632
Plan Check / Job No.
B20LA23465
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED REMODEL AND ADDITION TO EXISTING SINGLE FAMILY RESIDENCE.
Permit Issued
Issued on 4/20/2021
Issuing Office
Current Status
CofO Issued on 1/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 SINA KHOSRAVI
Corrections Issued 12/27/2020 SINA KHOSRAVI
Applicant returned to address corrections 2/22/2021 CRISTINA SALAZAR
Applicant returned to address corrections 3/12/2021 RAHEL BEYENE
Applicant returned to address corrections 3/18/2021 RAHEL BEYENE
Applicant returned to address corrections 4/13/2021 CRISTINA SALAZAR
Plan Check Approved 4/14/2021 CRISTINA SALAZAR
Building Plans Picked Up 4/15/2021 APPLICANT
Issued 4/20/2021 APPLICANT
CofO in Progress 1/13/2022 STUART CHAPMAN
No Progress 1/13/2022 SCOTT FINNILA
CofO in Progress 1/27/2022 STUART CHAPMAN
Permit Finaled 1/29/2022 DEROLD HAUFF
CofO Issued 1/29/2022 DEROLD HAUFF
Permit Finaled 1/29/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/27/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 1/27/2021 JEANIE LAM
Sewer availability Cleared 2/9/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/4/2021 Approved STUART CHAPMAN
Deputy Drilled-In Anchors 5/21/2021 Approved JESUS PINEDA
Footing/Foundation/Slab 5/21/2021 Approved STUART CHAPMAN
PLUMBING-Rough 6/22/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 7/1/2021 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 7/13/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 7/13/2021 Approved STUART CHAPMAN
HVAC-Rough 7/13/2021 Approved STUART CHAPMAN
PLUMBING-Rough 7/13/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 7/27/2021 Partial Approval RICHARD STEINBACH
Interior/Exterior Lathing 8/4/2021 Approved CALEB MEISTER
ELECTRICAL-Rough 8/16/2021 Approved STUART CHAPMAN
Insulation 8/23/2021 Corrections Issued CALEB MEISTER
Shower Pan 8/23/2021 Approved CALEB MEISTER
Insulation 8/25/2021 Approved CALEB MEISTER
Drywall Nailing 9/7/2021 Approved SABAS ALONSO
Underground Mechanical 10/8/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 12/22/2021 Approved STUART CHAPMAN
Final 12/22/2021 Corrections Issued STUART CHAPMAN
Green Building Final 12/22/2021 Approved STUART CHAPMAN
Green Building Rough 12/22/2021 Approved STUART CHAPMAN
MERV13>=Final 12/22/2021 Approved STUART CHAPMAN
MERV13>=Rough 12/22/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 12/22/2021 SGSOV Approved STUART CHAPMAN
Smoke Detectors 12/22/2021 Not Ready for Inspection STUART CHAPMAN
Gas Test 12/29/2021 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 1/5/2022 Approved STUART CHAPMAN
Final 1/5/2022 OK to Issue CofO STUART CHAPMAN
Green Building Final 1/5/2022 Approved STUART CHAPMAN
HVAC-Final 1/5/2022 Approved STUART CHAPMAN
PLUMBING-Final 1/5/2022 Approved STUART CHAPMAN
Smoke Detectors 1/5/2022 Approved STUART CHAPMAN
Service/Power Release 1/14/2022 Approved SCOTT FINNILA
Special/Order Compliance 1/27/2022 Approved STUART CHAPMAN