1100 N NORTH MAIN ST 90012
Certificate Information: 1100 N NORTH MAIN ST 90012
- Application / Permit
- 20014-10000-05620
- Plan Check / Job No.
- B20LA23425
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- 1492 SOLAR PV MODULES FOR A 671.4 kW DC SYSTEM SIZE ON AN EXISTING BUILDING. No structural foundation changes will be done as a part of this scope of work
- Permit Issued
- Issued on 5/27/2021
- Issuing Office
- Current Status
- Issued on 5/27/2021
Permit Application Status History
| Submitted | 12/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2021 | ZAW HAN |
| Corrections Issued | 1/25/2021 | ZAW HAN |
| Quality Review Completed | 2/2/2021 | GARO TELMI |
| Applicant returned to address corrections | 4/30/2021 | ZAW HAN |
| Plan Check Approved | 5/5/2021 | ZAW HAN |
| Plan Check Approved | 5/27/2021 | ZAW HAN |
| Issued | 5/27/2021 | APPLICANT |
| Building Plans Picked Up | 6/2/2021 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 2/25/2021 | OSVALDO GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2021 | RENZ SORIANO |
| Low Impact Development | Cleared | 3/11/2021 | ORVAL HERNANDEZ-MARCIAL |
| Miscellaneous | Cleared | 4/22/2021 | OSCAR SALGADO JR |
| Roof/Waste drainage to street | Cleared | 4/22/2021 | ROSA SILVA |
Contact Information
| Contractor | Sungreen Systems Inc; Lic. No.: 935910-B | 202 S LAKE AVE STE 300 PASADENA, CA 91706 |
| Engineer | Truong,, Phong Lap; Lic. No.: C70784 | 20754 TIMBERLINE LN WALNUT, CA 91789 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/10/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 7/8/2021 | Conditional Approval | MARK FERRARI |
| Deputy Other (see comments) | 7/8/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 7/8/2021 | Conditional Approval | MARK FERRARI |
| Pre-Inspection | 7/8/2021 | Partial Inspection | MARK FERRARI |
| Pre-Inspection | 7/20/2021 | Conditional Approval | MARK FERRARI |
| Final | 8/17/2021 | Not Ready for Inspection | LANNY MERRICK |
| Green Building Final | 8/17/2021 | Not Ready for Inspection | LANNY MERRICK |
| SGSOV-Seismic Gas S/O Valve | 8/17/2021 | SGSOV Not Ready | LANNY MERRICK |
| Smoke Detectors | 8/17/2021 | Not Ready for Inspection | LANNY MERRICK |
| Footing/Foundation/Slab | 8/24/2021 | Approved | LANNY MERRICK |
| Final | 11/24/2021 | Corrections Issued | MARK FERRARI |
| Green Building Final | 11/24/2021 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 11/24/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 11/24/2021 | Approved | MARK FERRARI |