4511 1/2 N ALPHA ST 90032
Certificate Information: 4511 1/2 N ALPHA ST 90032
- Application / Permit
- 20014-10000-05604
- Plan Check / Job No.
- B20LA23370
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) RECRATION ROOM TO (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/8/2023
- Issuing Office
- Metro
- Current Status
- Issued on 6/8/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/15/2021 | DANIEL YIP |
| Corrections Issued | 1/21/2021 | DANIEL YIP |
| Quality Review Completed | 2/2/2021 | ALLEN MANALANSAN |
| Building Plans Picked Up | 2/5/2021 | APPLICANT |
| Plan Check Approved | 6/8/2023 | DANIEL YIP |
| Issued | 6/8/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2021 | CELINA MORENO |
| Sewer availability | Cleared | 3/11/2021 | CELINA MORENO |
| City Hist. Cultural Monument | Cleared | 1/12/2023 | DAMIAN GATTO |
| HPOZ | Cleared | 1/12/2023 | DAMIAN GATTO |
| Historic monument | Cleared | 1/12/2023 | DAMIAN GATTO |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2023 | CELINA MORENO |
Contact Information
| Contractor | M And C Building Designs Inc; Lic. No.: 1074949-B | 38 UMBRIA IRVINE, CA 92618 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/13/2023 | Conditional Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2023 | Approved | AMY COLIN |
| Footing/Foundation/Slab | 7/20/2023 | Corrections Issued | AMY COLIN |
| Wood Frame | 7/20/2023 | Partial Approval | AMY COLIN |
| Deputy Reinf. Concrete | 7/27/2023 | Conditional Approval | AMY COLIN |
| BUILDING-Rough-Frame | 8/2/2023 | Not Ready for Inspection | AMY COLIN |
| ELECTRICAL-Rough | 8/2/2023 | Corrections Issued | AMY COLIN |
| PLUMBING-Rough | 8/2/2023 | Corrections Issued | AMY COLIN |
| Wood Frame | 8/2/2023 | Partial Approval | AMY COLIN |
| ELECTRICAL-Rough | 8/8/2023 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2023 | Approved | AMY COLIN |
| PLUMBING-Rough | 8/8/2023 | Approved | AMY COLIN |
| Wood Frame | 8/8/2023 | Approved | AMY COLIN |
| Insulation | 10/10/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 10/10/2023 | Partial Approval | AMY COLIN |
| Drywall Nailing | 11/13/2023 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 11/20/2025 | Approved | DAVID WILLIAMS |
| Sewer | 1/29/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Sewer | 2/5/2026 | Approved | ALIZAH MAYAGOITIA |