13046 W JOUETT ST 91331

Certificate Information: 13046 W JOUETT ST 91331

Application / Permit
20014-10000-05581
Plan Check / Job No.
B20LA23295
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Add new ADU to 2nd floor over existing garage
Permit Issued
Issued on 9/2/2021
Issuing Office
Current Status
CofO Issued on 4/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 ARSALAN SHABESTARI
Corrections Issued 1/19/2021 ARSALAN SHABESTARI
Quality Review Completed 2/2/2021 HERNAN ARREOLA
Applicant returned to address corrections 4/24/2021 ARSALAN SHABESTARI
Plan Check Approved 8/30/2021 ARSALAN SHABESTARI
Issued 9/2/2021 APPLICANT
CofO in Progress 4/7/2022 MICHEL ABAJAN
Permit Finaled 4/8/2022 RONALD MYRICK
CofO Issued 4/8/2022 RONALD MYRICK
Permit Finaled 4/8/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 2/24/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/24/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/24/2021 JOHN TRIANTAFYLLOS
ZI Cleared 5/20/2021 MIGUEL GAMBOA
Low Impact Development Cleared 8/3/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 8/4/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/2/2021 Partial Approval MICHEL ABAJAN
METHANE-Barrier 11/2/2021 Approved MICHEL ABAJAN
METHANE-Subgrade 11/2/2021 Approved MICHEL ABAJAN
Footing/Foundation/Slab 11/8/2021 Approved MICHEL ABAJAN
Wood Frame 11/12/2021 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/1/2021 Partial Approval GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 12/16/2021 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 12/21/2021 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Rough 12/21/2021 Approved DAVID MATSON
HVAC-Rough 12/21/2021 Corrections Issued DAVID MATSON
METHANE-Rough 12/21/2021 Approved DAVID MATSON
PLUMBING-Rough 12/21/2021 Corrections Issued DAVID MATSON
Wood Frame 12/21/2021 Not Ready for Inspection DAVID MATSON
BUILDING-Rough-Frame 12/22/2021 Approved MICHEL ABAJAN
Green Building Rough 12/22/2021 Approved MICHEL ABAJAN
METHANE-Rough 12/22/2021 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 12/22/2021 Approved MICHEL ABAJAN
Insulation 12/27/2021 No Access for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 12/27/2021 No Access for Inspection MICHEL ABAJAN
Drywall Nailing 1/4/2022 Approved JESUS RODRIGUEZ
Insulation 1/4/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 1/4/2022 Approved JESUS RODRIGUEZ
Underground Mechanical 2/2/2022 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 3/22/2022 Corrections Issued MICHEL ABAJAN
Final 3/22/2022 Corrections Issued MICHEL ABAJAN
HVAC-Final 3/22/2022 Approved MICHEL ABAJAN
PLUMBING-Final 3/22/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/22/2022 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 3/22/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 4/7/2022 Approved MICHEL ABAJAN
Final 4/7/2022 OK to Issue CofO MICHEL ABAJAN