21919 S HALLDALE AVE 90501
Certificate Information: 21919 S HALLDALE AVE 90501
- Application / Permit
- 20014-10000-05580
- Plan Check / Job No.
- B20LA23294
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: NEW ATTACHED ADU ADDITION TO (E) SFD, ABOVE (E) GARAGE
- Permit Issued
- Issued on 2/3/2022
- Issuing Office
- Current Status
- CofO Issued on 12/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/15/2021 | GARO TELMI |
| Corrections Issued | 2/2/2021 | GARO TELMI |
| Quality Review Completed | 2/3/2021 | HERNAN ARREOLA |
| Plan Check Approved | 1/31/2022 | GARO TELMI |
| Issued | 2/3/2022 | APPLICANT |
| CofO in Progress | 12/13/2023 | EUGENE CASSIDY |
| Permit Finaled | 12/14/2023 | DONALD CRICHLOW |
| CofO Issued | 12/14/2023 | DONALD CRICHLOW |
| Permit Finaled | 12/14/2023 | DONALD CRICHLOW |
Permit Application Clearance Information
| Address approval | Cleared | 2/9/2021 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2021 | CHINH DINH |
| Sewer availability | Cleared | 3/31/2021 | CHINH DINH |
| Low Impact Development | Cleared | 10/25/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 1/7/2022 | JOSE HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hale,, Ronald Richard; Lic. No.: NA17056 | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/27/2022 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/28/2022 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 6/28/2022 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/16/2022 | Corrections Issued | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2022 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 8/16/2022 | Approved | EUGENE CASSIDY |
| Posting Pre-Inspection | 8/16/2022 | Approved | EUGENE CASSIDY |
| Insulation | 8/31/2022 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/16/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 11/16/2022 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 11/16/2022 | Approved | EUGENE CASSIDY |
| Insulation | 11/16/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 11/30/2022 | Not Ready for Inspection | JOHN KLARIN |
| Interior/Exterior Lathing | 11/30/2022 | Corrections Issued | JOHN KLARIN |
| Drywall Nailing | 12/6/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/6/2022 | Approved | EUGENE CASSIDY |
| Service/Power Release | 8/1/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 8/4/2023 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/4/2023 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 8/4/2023 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 8/4/2023 | Approved | EUGENE CASSIDY |
| Final | 8/15/2023 | Corrections Issued | EUGENE CASSIDY |
| Final | 10/24/2023 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/12/2023 | Approved | EUGENE CASSIDY |
| Final | 12/12/2023 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 12/12/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 12/12/2023 | Approved | EUGENE CASSIDY |