151 S CITRUS AVE 90036

Certificate Information: 151 S CITRUS AVE 90036

Application / Permit
20014-10000-05576
Plan Check / Job No.
B20LA23271
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDITION TO (E) 1ST AND 2ND STORIES SINGLE FAMILY DWELLING
Permit Issued
Issued on 3/10/2021
Issuing Office
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 DANIEL YIP
Corrections Issued 1/5/2021 DANIEL YIP
Quality Review Completed 1/12/2021 ALLEN MANALANSAN
Building Plans Picked Up 1/15/2021 APPLICANT
Plan Check Approved 3/10/2021 DANIEL YIP
Issued 3/10/2021 APPLICANT
CofO in Progress 12/9/2022 RICHARD DOCKUS
Permit Finaled 12/17/2022 DEROLD HAUFF
CofO Issued 12/17/2022 DEROLD HAUFF
Permit Finaled 12/17/2022 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 1/21/2021 RUBEN VASQUEZ
ZA Case Cleared 1/21/2021 RUBEN VASQUEZ
Abandoned oil well Cleared 2/8/2021 ROBERT DUFF

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 6/10/2021 Approved JOSEPH MCGARRY
Deputy Drilled-In Anchors 7/28/2021 Conditional Approval CHARLES BOGHOSKHAN
Deputy Drilled-In Anchors 9/27/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/4/2022 Partial Approval CHRIS CHRISTENSEN
Pre-Inspection 1/4/2022 Approved CHRIS CHRISTENSEN
Deputy Wood Construction 1/12/2022 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 1/28/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 1/28/2022 Approved ARTHUR SARGSYAN
Green Building Rough 1/28/2022 Approved ARTHUR SARGSYAN
HVAC-Rough 1/28/2022 Approved ARTHUR SARGSYAN
METHANE-Rough 1/28/2022 Approved ARTHUR SARGSYAN
PLUMBING-Rough 1/28/2022 Approved ARTHUR SARGSYAN
Pre-Inspection 2/14/2022 Corrections Issued SHAVONNE ESPINOZA
Insulation 3/1/2022 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 3/23/2022 Approved ARTHUR SARGSYAN
Drywall Nailing 4/4/2022 Approved ARTHUR SARGSYAN
Pre-Inspection 6/7/2022 Conditional Approval ADAM ESCOTO
Final 8/5/2022 Not Ready for Inspection JEFFREY MEAD
Footing/Foundation/Slab 8/5/2022 Approved JEFFREY MEAD
Green Building Final 8/5/2022 Partial Approval JEFFREY MEAD
METHANE-Barrier 8/5/2022 Approved JEFFREY MEAD
METHANE-Subgrade 8/5/2022 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 8/5/2022 SGSOV Approved JEFFREY MEAD
Smoke Detectors 8/5/2022 Approved JEFFREY MEAD
Final 12/8/2022 OK to Issue CofO RICHARD DOCKUS
Green Building Final 12/8/2022 Approved RICHARD DOCKUS