5236 W SANCHEZ DR 90008

Certificate Information: 5236 W SANCHEZ DR 90008

Application / Permit
20014-10000-05571
Plan Check / Job No.
B20LA23246
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION (17.5 ft x 39.67ft, 688 sqft) TO EXISTING ONE STORY SFD.
Permit Issued
Issued on 4/22/2021
Issuing Office
Current Status
Issued on 4/22/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/6/2021 APPLICANT
Assigned to Plan Check Engineer 1/7/2021 TSE MING HUANG
Corrections Issued 1/9/2021 TSE MING HUANG
Applicant returned to address corrections 3/18/2021 RAHEL BEYENE
Applicant returned to address corrections 4/16/2021 LUKE GONZALES
Plan Check Approved 4/21/2021 LUKE GONZALES
Plan Check Approved 4/21/2021 LUKE GONZALES
Issued 4/22/2021 APPLICANT
Building Plans Picked Up 4/28/2021 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 1/22/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 1/25/2021 RENZ SORIANO
Low Impact Development Cleared 3/31/2021 YVAINNE GALSIM
Grading Pre-Inspection Cleared 4/16/2021 LUKE GONZALES
Roof/Waste drainage to street Cleared 4/19/2021 ROSA SILVA

Contact Information

Contractor Valencia Construction Company; Lic. No.: 1015167-B 12069 SMALLWOOD AVE      DOWNEY, CA 90242
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/26/2021 Approved DAVID FEILER
Excavation/Setback/Form/Re-Bar 5/26/2021 Approved DAVID FEILER
Footing/Foundation/Slab 5/26/2021 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 6/2/2021 Partial Approval DAVID FEILER
Insulation 6/3/2021 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 7/9/2021 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 7/9/2021 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 7/9/2021 Approved JOAQUIN GREENOUGH
Green Building Rough 7/9/2021 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 7/9/2021 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 7/9/2021 Corrections Issued JOAQUIN GREENOUGH
Deputy Wood Construction 7/12/2021 No Access for Inspection ELMER BLAND
BUILDING-Rough-Frame 7/13/2021 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 7/13/2021 Approved DAVID FEILER
Green Building Rough 7/13/2021 Approved DAVID FEILER
HVAC-Rough 7/13/2021 Approved DAVID FEILER
Interior/Exterior Lathing 7/13/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 7/13/2021 Approved DAVID FEILER
Insulation 7/15/2021 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 7/15/2021 Partial Approval JESUS RODRIGUEZ
Drywall Nailing 7/19/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 7/19/2021 Corrections Issued JOAQUIN GREENOUGH
Drywall Nailing 7/20/2021 Approved DAVID FEILER
Green Building Rough 7/20/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 10/25/2021 No Access for Inspection ANTHONY EGSON
ELECTRICAL-Final 10/25/2021 No Access for Inspection ANTHONY EGSON
Final 10/25/2021 No Access for Inspection ANTHONY EGSON
Green Building Final 10/25/2021 No Access for Inspection ANTHONY EGSON
HVAC-Final 10/25/2021 No Access for Inspection ANTHONY EGSON
PLUMBING-Final 10/25/2021 No Access for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 10/25/2021 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 10/25/2021 No Access for Inspection ANTHONY EGSON
ELECTRICAL-Final 10/27/2021 Corrections Issued ANTHONY EGSON
HVAC-Final 10/27/2021 Corrections Issued ANTHONY EGSON
PLUMBING-Final 10/27/2021 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 10/29/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 10/29/2021 Approved STUART CHAPMAN
Final 10/29/2021 Corrections Issued STUART CHAPMAN
Green Building Final 10/29/2021 Approved STUART CHAPMAN
HVAC-Final 10/29/2021 Approved STUART CHAPMAN
PLUMBING-Final 10/29/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/29/2021 SGSOV Approved STUART CHAPMAN
Smoke Detectors 10/29/2021 Approved STUART CHAPMAN