5236 W SANCHEZ DR 90008
Certificate Information: 5236 W SANCHEZ DR 90008
- Application / Permit
- 20014-10000-05571
- Plan Check / Job No.
- B20LA23246
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION (17.5 ft x 39.67ft, 688 sqft) TO EXISTING ONE STORY SFD.
- Permit Issued
- Issued on 4/22/2021
- Issuing Office
- Current Status
- Issued on 4/22/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | TSE MING HUANG |
| Corrections Issued | 1/9/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 3/18/2021 | RAHEL BEYENE |
| Applicant returned to address corrections | 4/16/2021 | LUKE GONZALES |
| Plan Check Approved | 4/21/2021 | LUKE GONZALES |
| Plan Check Approved | 4/21/2021 | LUKE GONZALES |
| Issued | 4/22/2021 | APPLICANT |
| Building Plans Picked Up | 4/28/2021 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 1/22/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2021 | RENZ SORIANO |
| Low Impact Development | Cleared | 3/31/2021 | YVAINNE GALSIM |
| Grading Pre-Inspection | Cleared | 4/16/2021 | LUKE GONZALES |
| Roof/Waste drainage to street | Cleared | 4/19/2021 | ROSA SILVA |
Contact Information
| Contractor | Valencia Construction Company; Lic. No.: 1015167-B | 12069 SMALLWOOD AVE DOWNEY, CA 90242 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/26/2021 | Approved | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 5/26/2021 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 5/26/2021 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2021 | Partial Approval | DAVID FEILER |
| Insulation | 6/3/2021 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/9/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 7/9/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 7/9/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Rough | 7/9/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 7/9/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 7/12/2021 | No Access for Inspection | ELMER BLAND |
| BUILDING-Rough-Frame | 7/13/2021 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 7/13/2021 | Approved | DAVID FEILER |
| Green Building Rough | 7/13/2021 | Approved | DAVID FEILER |
| HVAC-Rough | 7/13/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 7/13/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 7/13/2021 | Approved | DAVID FEILER |
| Insulation | 7/15/2021 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/15/2021 | Partial Approval | JESUS RODRIGUEZ |
| Drywall Nailing | 7/19/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 7/19/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Drywall Nailing | 7/20/2021 | Approved | DAVID FEILER |
| Green Building Rough | 7/20/2021 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 10/25/2021 | No Access for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 10/25/2021 | No Access for Inspection | ANTHONY EGSON |
| Final | 10/25/2021 | No Access for Inspection | ANTHONY EGSON |
| Green Building Final | 10/25/2021 | No Access for Inspection | ANTHONY EGSON |
| HVAC-Final | 10/25/2021 | No Access for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 10/25/2021 | No Access for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 10/25/2021 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 10/25/2021 | No Access for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 10/27/2021 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 10/27/2021 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 10/27/2021 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/29/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 10/29/2021 | Approved | STUART CHAPMAN |
| Final | 10/29/2021 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 10/29/2021 | Approved | STUART CHAPMAN |
| HVAC-Final | 10/29/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 10/29/2021 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 10/29/2021 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 10/29/2021 | Approved | STUART CHAPMAN |