12836 W BONAPARTE AVE 90066

Certificate Information: 12836 W BONAPARTE AVE 90066

Application / Permit
20014-10000-05563
Plan Check / Job No.
B20LA23205
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Ground floor addition and remodeling to 1-story SFD.
Permit Issued
Issued on 10/11/2021
Issuing Office
Current Status
CofO Issued on 5/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 JOE VO
Corrections Issued 12/26/2020 JOE VO
Quality Review Completed 1/21/2021 KEN GILL
Building Plans Picked Up 1/28/2021 APPLICANT
Plan Check Approved 9/8/2021 JOE VO
Issued 10/11/2021 APPLICANT
CofO in Progress 5/22/2023 HERBERT GIRON
Permit Finaled 5/30/2023 DANIEL ORRANTE
CofO Issued 5/30/2023 DANIEL ORRANTE
Permit Finaled 5/30/2023 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 8/6/2021 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 10/4/2021 DENNIS BRAGIN
Roof/Waste drainage to street Cleared 10/4/2021 ANTHONY MAINEZ
Sewer availability Cleared 10/4/2021 DENNIS BRAGIN
Construction near power lines Cleared 10/8/2021 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/20/2022 Not Ready for Inspection JESUS RODRIGUEZ
Deputy Drilled-In Anchors 5/13/2022 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 5/16/2022 Partial Approval JESUS RODRIGUEZ
METHANE-Barrier 5/16/2022 Conditional Approval JESUS RODRIGUEZ
METHANE-Subgrade 5/16/2022 Conditional Approval JESUS RODRIGUEZ
Deputy Drilled-In Anchors 6/27/2022 Conditional Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 6/30/2022 Partial Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 6/30/2022 Corrections Issued JESUS RODRIGUEZ
Insulation 6/30/2022 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/17/2022 Approved HERBERT GIRON
Footing/Foundation/Slab 8/19/2022 Partial Approval HERBERT GIRON
METHANE-Barrier 8/19/2022 Conditional Approval HERBERT GIRON
METHANE-Subgrade 8/19/2022 Conditional Approval HERBERT GIRON
Final 9/9/2022 Corrections Issued HERBERT GIRON
HVAC-Rough 9/9/2022 Corrections Issued HERBERT GIRON
PLUMBING-Rough 9/9/2022 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 9/13/2022 Corrections Issued HERBERT GIRON
PLUMBING-Rough 9/13/2022 Approved HERBERT GIRON
ELECTRICAL-Rough 9/19/2022 Approved HERBERT GIRON
HVAC-Rough 9/19/2022 Approved HERBERT GIRON
Deputy Wood Construction 9/22/2022 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/23/2022 Conditional Approval HERBERT GIRON
BUILDING-Rough-Frame 10/20/2022 Partial Approval HERBERT GIRON
Insulation 10/20/2022 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 11/3/2022 Conditional Approval HERBERT GIRON
Green Building Rough 11/3/2022 Conditional Approval HERBERT GIRON
Interior/Exterior Lathing 11/3/2022 Conditional Approval HERBERT GIRON
METHANE-Rough 11/3/2022 Approved HERBERT GIRON
Deputy Wood Construction 11/16/2022 Conditional Approval HERBERT GIRON
BUILDING-Rough-Frame 11/18/2022 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/18/2022 Approved HERBERT GIRON
Green Building Rough 11/18/2022 Partial Approval HERBERT GIRON
Insulation 11/18/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 11/18/2022 Partial Approval HERBERT GIRON
Drywall Nailing 12/6/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 12/12/2022 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 12/19/2022 Conditional Approval JESUS RODRIGUEZ
Shower Pan 12/19/2022 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 12/21/2022 Approved HERBERT GIRON
Shower Pan 12/21/2022 Approved HERBERT GIRON
Service/Power Release 3/2/2023 Not Ready for Inspection HERBERT GIRON
Underground Mechanical 3/2/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 4/21/2023 Approved HERBERT GIRON
ELECTRICAL-Final 4/21/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 4/21/2023 Approved HERBERT GIRON
Green Building Rough 4/21/2023 Approved HERBERT GIRON
METHANE-Barrier 4/21/2023 Approved HERBERT GIRON
METHANE-Subgrade 4/21/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 4/21/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 4/21/2023 Approved HERBERT GIRON
ELECTRICAL-Final 4/28/2023 Approved HERBERT GIRON
HVAC-Final 4/28/2023 Approved HERBERT GIRON
PLUMBING-Final 4/28/2023 Corrections Issued HERBERT GIRON
Final 5/2/2023 Corrections Issued HERBERT GIRON
Green Building Final 5/2/2023 Approved HERBERT GIRON
HVAC-Final 5/2/2023 Approved HERBERT GIRON
Final 5/4/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 5/4/2023 Approved HERBERT GIRON
Service/Power Release 5/8/2023 Corrections Issued HERBERT GIRON
Final 5/22/2023 OK to Issue CofO HERBERT GIRON
Service/Power Release 5/22/2023 Approved HERBERT GIRON