8010 S STANFORD AVE 90001
Certificate Information: 8010 S STANFORD AVE 90001
- Application / Permit
- 20014-10000-05551
- Plan Check / Job No.
- B20LA23172
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT WITH ADDITION (16'-0" X 22'-8").
- Permit Issued
- Issued on 3/18/2021
- Issuing Office
- Current Status
- CofO Issued on 12/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2020 | LAWRENCE QUIRANTE |
| Corrections Issued | 12/26/2020 | LAWRENCE QUIRANTE |
| Plan Check Approved | 2/25/2021 | FARSHAD ALIMOHAMADI |
| Issued | 3/18/2021 | APPLICANT |
| Building Plans Picked Up | 3/19/2021 | APPLICANT |
| CofO in Progress | 12/9/2021 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 12/17/2021 | DEROLD HAUFF |
| CofO Issued | 12/17/2021 | DEROLD HAUFF |
| Permit Finaled | 12/17/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/3/2021 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 2/3/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2021 | THOMAS LANG |
| Sewer availability | Cleared | 2/16/2021 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/6/2021 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 5/19/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 5/25/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 5/25/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 6/1/2021 | Corrections Issued | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 6/2/2021 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/2/2021 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/9/2021 | Corrections Issued | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2021 | Partial Approval | EUGENE CASSIDY |
| HVAC-Rough | 7/9/2021 | Approved | EUGENE CASSIDY |
| Insulation | 7/9/2021 | Conditional Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 7/9/2021 | Corrections Issued | EUGENE CASSIDY |
| Wood Frame | 7/9/2021 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/12/2021 | Approved | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2021 | Approved | ANSON MAGLASANG |
| HVAC-Rough | 7/12/2021 | Approved | ANSON MAGLASANG |
| Insulation | 7/12/2021 | Approved | ANSON MAGLASANG |
| PLUMBING-Rough | 7/12/2021 | Approved | ANSON MAGLASANG |
| Wood Frame | 7/12/2021 | Approved | ANSON MAGLASANG |
| Drywall Nailing | 7/26/2021 | Approved | CALEB MEISTER |
| ELECTRICAL-Rough | 7/26/2021 | Not Ready for Inspection | CALEB MEISTER |
| Interior/Exterior Lathing | 7/26/2021 | Approved | CALEB MEISTER |
| ELECTRICAL-Rough | 7/29/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/3/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/4/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/24/2021 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 9/3/2021 | Approved | JOHN KLARIN |
| Service/Power Release | 9/15/2021 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 9/24/2021 | Approved | SABAS ALONSO |
| Final | 9/24/2021 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 9/24/2021 | Approved | SABAS ALONSO |
| Green Building Final | 9/24/2021 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 9/24/2021 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/24/2021 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 9/24/2021 | Approved | SABAS ALONSO |
| Smoke Detectors | 9/24/2021 | Approved | SABAS ALONSO |
| Final | 11/2/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 11/2/2021 | Approved | JOAQUIN GREENOUGH |
| Final | 11/8/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 11/24/2021 | Corrections Issued | ANTHONY EGSON |
| Final | 12/3/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/8/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/8/2021 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/8/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/8/2021 | Approved | ALEJANDRO DE ARTOLA |