3807 W 60TH ST 90043
Certificate Information: 3807 W 60TH ST 90043
- Application / Permit
- 20014-10000-05530
- Plan Check / Job No.
- B20LA23086
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY MASTER BEDROOM/BATHROOM ADDITION (387 SQFT ADDITION) AND KITCHEN REMODEL. ADD FRONT PORCH. PC refer to comment
- Permit Issued
- Issued on 3/10/2021
- Issuing Office
- Metro
- Current Status
- Issued on 3/10/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2020 | JESSE JIMENEZ |
| Corrections Issued | 12/30/2020 | JESSE JIMENEZ |
| Applicant returned to address corrections | 2/10/2021 | CRISTINA SALAZAR |
| Plan Check Approved | 3/1/2021 | ADAM HEGAZI |
| Issued | 3/10/2021 | APPLICANT |
| Building Plans Picked Up | 3/11/2021 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/2/2021 | JEANIE LAM |
| Sewer availability | Cleared | 2/2/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2021 | JEANIE LAM |
Contact Information
| Contractor | Konstro Developers Builders; Lic. No.: 793954-B | 1608 CENTINELA AVENUE #13 INGLEWOOD, CA 90302 |
| Engineer | Adefeso,, Wole Dayo; Lic. No.: C63361 | 1608 CENTINELA AVE #13 INGLEWOOD, CA 90302 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/17/2021 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 3/22/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 4/8/2021 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/19/2021 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 4/19/2021 | Order to Comply Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/24/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/24/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 5/24/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 5/24/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 5/24/2021 | Approved | FREDDIE RIVERA |
| Insulation | 6/28/2021 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 6/28/2021 | Approved | CALEB MEISTER |
| Shower Pan | 7/2/2021 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 7/6/2021 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 7/12/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Drywall Nailing | 7/27/2021 | Approved | JESUS PINEDA |
| Shower Pan | 7/27/2021 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 8/13/2021 | Partial Approval | ADAM ESCOTO |
| Final | 12/28/2021 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 12/28/2021 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 12/28/2021 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 12/28/2021 | Approved | STUART CHAPMAN |