5729 W COLISEUM ST 90016

Certificate Information: 5729 W COLISEUM ST 90016

Application / Permit
20014-10000-05529
Plan Check / Job No.
B20LA23080
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL OF 1-STORY SFD: Add closet and laundry room extension.
Permit Issued
Issued on 7/31/2021
Issuing Office
Current Status
CofO Issued on 4/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2020 APPLICANT
Assigned to Plan Check Engineer 12/29/2020 JESSE JIMENEZ
Corrections Issued 12/30/2020 JESSE JIMENEZ
Plan Check Approved 3/22/2021 RICARDO RAMIREZ
Issued 7/31/2021 APPLICANT
Building Plans Picked Up 8/5/2021 APPLICANT
CofO in Progress 4/23/2024 ANTHONY EGSON
CofO Issued 4/29/2024 DEROLD HAUFF
Permit Finaled 4/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/24/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 3/2/2021 CECILIO NAVARRO
Grading Pre-Inspection Cleared 3/22/2021 JESSE JIMENEZ

Contact Information

Contractor A B C O Pacific Builders Inc; Lic. No.: 990998-B 5444 CRENSHAW BLVD      LOS ANGELES, CA 90043
Engineer Adefeso,, Wole Dayo; Lic. No.: C63361 1608 CENTINELA AVE #13      INGLEWOOD, CA 90302

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Insulation 10/12/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 10/12/2022 Approved ANTHONY EGSON
Drywall Nailing 11/9/2022 Approved ANTHONY EGSON
Shower Pan 3/21/2023 No Access for Inspection ANTHONY EGSON
Shower Pan 3/29/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 1/22/2024 Approved ANTHONY EGSON
Final 1/22/2024 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 1/22/2024 Approved ANTHONY EGSON
Green Building Final 1/22/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 1/22/2024 Approved ANTHONY EGSON
METHANE-Barrier 1/22/2024 Approved ANTHONY EGSON
METHANE-Final 1/22/2024 Approved ANTHONY EGSON
METHANE-Rough 1/22/2024 Approved ANTHONY EGSON
METHANE-Subgrade 1/22/2024 Approved ANTHONY EGSON
PLUMBING-Final 1/22/2024 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 1/22/2024 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 1/22/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 4/10/2024 Approved ANTHONY EGSON
HVAC-Rough 4/10/2024 Approved ANTHONY EGSON
Final 4/23/2024 OK to Issue CofO ANTHONY EGSON
Green Building Final 4/23/2024 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 4/23/2024 SGSOV Approved ANTHONY EGSON