23847 W CROSSON DR 91367

Certificate Information: 23847 W CROSSON DR 91367

Application / Permit
20014-10000-05523
Plan Check / Job No.
B20LA23052
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO (E) SFD, CONVERT PORTION OF GARAGE INTO NEW PANTRY AND NEW POWDER ROOM.
Permit Issued
Issued on 1/21/2021
Issuing Office
Current Status
CofO Issued on 10/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2020 APPLICANT
Assigned to Plan Check Engineer 12/21/2020 FERNANDO FLORES
Corrections Issued 12/22/2020 FERNANDO FLORES
Plan Check Approved 1/19/2021 SHANGQIN XIE
Issued 1/21/2021 APPLICANT
Building Plans Picked Up 1/27/2021 APPLICANT
CofO in Progress 5/12/2021 TROY SANDERS
CofO Issued 10/14/2021 JOHN JANSON
Permit Finaled 10/14/2021 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/29/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/30/2020 ADRIAN CASTRO
Sewer availability Cleared 12/30/2020 ADRIAN CASTRO
Grading Pre-Inspection Cleared 1/12/2021 PATRICK MISCHLICH

Contact Information

Contractor Dream Remodeling Inc; Lic. No.: 889254-B 22704 VENTURA BLVD #444      WOODLAND HILLS, CA 91411

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/27/2021 Approved TROY SANDERS
PLUMBING-Rough 2/1/2021 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/3/2021 Approved TROY SANDERS
ELECTRICAL-Rough 2/18/2021 Approved TROY SANDERS
PLUMBING-Rough 2/18/2021 Approved TROY SANDERS
Wood Frame 2/18/2021 Not Ready for Inspection TROY SANDERS
BUILDING-Rough-Frame 2/25/2021 Approved TROY SANDERS
Green Building Rough 2/25/2021 Approved TROY SANDERS
Interior/Exterior Lathing 2/25/2021 Partial Approval TROY SANDERS
Insulation 3/1/2021 Approved TROY SANDERS
Drywall Nailing 3/4/2021 Approved TROY SANDERS
Final 5/4/2021 Corrections Issued TROY SANDERS
Footing/Foundation/Slab 5/4/2021 Approved TROY SANDERS
Green Building Final 5/4/2021 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 5/4/2021 SGSOV Approved TROY SANDERS
Smoke Detectors 5/4/2021 Approved TROY SANDERS
ELECTRICAL-Final 5/11/2021 Approved TROY SANDERS
Final 5/11/2021 OK to Issue CofO TROY SANDERS
HVAC-Final 5/11/2021 Approved TROY SANDERS
PLUMBING-Final 5/11/2021 Approved TROY SANDERS