8109 S KENYON AVE 90045
Certificate Information: 8109 S KENYON AVE 90045
- Application / Permit
- 20014-10000-05519
- Plan Check / Job No.
- B20LA23034
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE (330SF) TO ADU + 1 STORY ADDITION (96 SF) & 2ND STORY ADDITION (289 SF) TOTAL ADU AREA = 715 SF PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- CofO Issued on 1/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 12/29/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 1/11/2021 | KESETE HAREGOT |
| Plan Check Approved | 3/1/2022 | SERGIO GUTIERREZ |
| Issued | 3/17/2022 | APPLICANT |
| Building Plans Picked Up | 4/1/2022 | APPLICANT |
| Refund in Progress | 8/30/2022 | TERENCE SHIA |
| Refund Withdrawn | 1/24/2023 | AGNES SONDERVAN |
| Issued | 1/24/2023 | AGNES SONDERVAN |
| CofO in Progress | 1/10/2024 | BOBBY KEY |
| Permit Finaled | 1/12/2024 | DANIEL ORRANTE |
| CofO Issued | 1/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/8/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2021 | DINAH GARIN |
| Sewer availability | Cleared | 2/23/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 4/14/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 5/18/2021 | RIDWAN HARDY |
| Specific Plan | Cleared | 6/25/2021 | PEDRO AYALA |
| Low Impact Development | Cleared | 10/28/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 11/19/2021 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Partial Approval | RICHARD STEINBACH |
| Insulation | 2/6/2023 | Partial Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 2/6/2023 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Partial Approval | BOBBY KEY |
| Final | 3/31/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 4/11/2023 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 4/14/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 4/14/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 4/18/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 4/18/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 4/18/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 6/7/2023 | Approved | BOBBY KEY |
| Green Building Rough | 6/7/2023 | Approved | BOBBY KEY |
| Insulation | 6/7/2023 | Approved | BOBBY KEY |
| Shower Pan | 6/7/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 6/13/2023 | Approved | BOBBY KEY |
| Underground Mechanical | 7/19/2023 | Approved | BOBBY KEY |
| Gas Test | 10/19/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 10/25/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Gas Test | 11/3/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 12/19/2023 | Corrections Issued | BOBBY KEY |
| Final | 12/19/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 12/19/2023 | Approved | BOBBY KEY |
| Green Building Final | 12/19/2023 | Approved | BOBBY KEY |
| HVAC-Final | 12/19/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 12/19/2023 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 12/19/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 1/10/2024 | Approved | BOBBY KEY |
| Final | 1/10/2024 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 1/10/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 1/10/2024 | Approved | BOBBY KEY |
| Special/Order Compliance | 1/10/2024 | Partial Inspection | BEN MOLSTAD |