424 N AVENUE 64 90042
Certificate Information: 424 N AVENUE 64 90042
- Application / Permit
- 20014-10000-05517
- Plan Check / Job No.
- B20LA23032
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert a SFD 2-car garage into a 2-story ADU Per L.A.M.C 12.22A.cc(c)-(d)
- Permit Issued
- Issued on 9/17/2021
- Issuing Office
- Current Status
- CofO Issued on 2/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | KHEDER ALRAZAA |
| Corrections Issued | 2/26/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 3/3/2021 | JASON HEALEY |
| Applicant returned to address corrections | 7/30/2021 | KHEDER ALRAZAA |
| No Progress | 8/27/2021 | KHEDER ALRAZAA |
| Plan Check Approved | 8/27/2021 | KHEDER ALRAZAA |
| Issued | 9/17/2021 | APPLICANT |
| Building Plans Picked Up | 10/8/2021 | APPLICANT |
| CofO in Progress | 2/3/2026 | DAVID WILLIAMS |
| Permit Finaled | 2/7/2026 | DEROLD HAUFF |
| CofO Issued | 2/7/2026 | DEROLD HAUFF |
| Permit Finaled | 2/7/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/15/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2021 | JEANIE LAM |
| Sewer availability | Cleared | 3/16/2021 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 4/5/2021 | PATRICK MISCHLICH |
| HPOZ | Cleared | 4/9/2021 | KATIE DEBIASE |
| ZI | Cleared | 4/9/2021 | KATIE DEBIASE |
| Hydrant and Access approval | Cleared | 5/11/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 7/16/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/27/2021 | JEANIE LAM |
| GPI Written Notices | Cleared | 8/3/2021 | KHEDER ALRAZAA |
Contact Information
| Contractor | Innovative Renovations Inc; Lic. No.: 542716-B | 2405 RIVERSIDE PLACE LOS ANGELES, CA 90039 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/7/2022 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/22/2022 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 5/17/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 6/16/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Deputy Drilled-In Anchors | 7/19/2022 | Conditional Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2022 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/5/2022 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 10/5/2022 | Approved | CRAIG VAUGHAN |
| Deputy Wood Construction | 10/6/2022 | Conditional Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 12/15/2022 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 12/16/2022 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Rough | 12/16/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 12/16/2022 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 1/5/2023 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 1/5/2023 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 1/17/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Insulation | 2/9/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Drywall Nailing | 3/17/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 4/21/2023 | Approved | CRAIG VAUGHAN |
| Sewer | 4/21/2023 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 6/22/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Special/Order Compliance | 9/30/2025 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 2/2/2026 | Approved | DAVID WILLIAMS |
| Final | 2/2/2026 | OK to Issue CofO | DAVID WILLIAMS |
| Green Building Final | 2/2/2026 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 2/2/2026 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 2/2/2026 | Approved | DAVID WILLIAMS |