1003 N TOLEDO ST 90042
Certificate Information: 1003 N TOLEDO ST 90042
- Application / Permit
- 20014-10000-05504
- Plan Check / Job No.
- B20LA22995
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXISTING COVER FRONT PORCH TO BE ENCLOSED AND CONVERTED INTO LIVING SPACE TO (E) ONE STORY SFD.
- Permit Issued
- Issued on 9/1/2021
- Issuing Office
- Current Status
- CofO Issued on 4/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2020 | TSE MING HUANG |
| Corrections Issued | 12/18/2020 | TSE MING HUANG |
| Plan Check Approved | 7/23/2021 | TSE MING HUANG |
| Issued | 9/1/2021 | APPLICANT |
| Building Plans Picked Up | 9/3/2021 | APPLICANT |
| CofO in Progress | 3/8/2022 | CRAIG VAUGHAN |
| CofO Issued | 4/25/2022 | DEROLD HAUFF |
| Permit Finaled | 4/25/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/18/2021 | THOMAS LANG |
| Grading Pre-Inspection | Cleared | 4/27/2021 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/2/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 12/2/2021 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 12/7/2021 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 12/7/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 12/7/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 12/7/2021 | Corrections Issued | CRAIG VAUGHAN |
| Insulation | 12/7/2021 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 12/7/2021 | Approved | CRAIG VAUGHAN |
| Wood Frame | 12/7/2021 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/15/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 12/15/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 12/15/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 12/15/2021 | Approved | CRAIG VAUGHAN |
| Wood Frame | 12/15/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 12/20/2021 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 12/20/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 12/28/2021 | Approved | CHARLES BOGHOSKHAN |
| ELECTRICAL-Final | 2/23/2022 | Approved | CRAIG VAUGHAN |
| Final | 2/23/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 2/23/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 2/23/2022 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Final | 2/23/2022 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 2/23/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 2/23/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/2/2022 | Approved | CRAIG VAUGHAN |
| Final | 3/2/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 3/2/2022 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Final | 3/2/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 3/2/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Final | 3/7/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 3/7/2022 | Approved | CRAIG VAUGHAN |