Application / Permit
20014-10000-05495
Plan Check / Job No.
B20LA22933
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
E-PLAN: Convert existing garage to accessory dwelling unit per state law GCS 65852.2(e)(1)(A) and addition to accessory dwelling unit
Permit Issued
Issued on 4/26/2021
Issuing Office
Current Status
CofO Issued on 2/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2020 APPLICANT
Assigned to Plan Check Engineer 12/17/2020 VU NGUYEN
Corrections Issued 12/17/2020 VU NGUYEN
Applicant returned to address corrections 3/27/2021 VU NGUYEN
Plan Check Approved 4/20/2021 VU NGUYEN
Issued 4/26/2021 APPLICANT
CofO in Progress 2/14/2022 JACK KARGODORIAN
Permit Finaled 2/17/2022 MICHAEL SMITH
CofO Issued 2/17/2022 MICHAEL SMITH
Permit Finaled 2/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/21/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 1/21/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/22/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/22/2021 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 3/20/2021 RIDWAN HARDY

Contact Information

Contractor Dhs Ventures Inc; Lic. No.: 1047699-B 3575 CAHUENGA BLVD #350      LOS ANGELES, CA 90068

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/3/2021 Not Ready for Inspection RICHARD DOCKUS
Footing/Foundation/Slab 6/9/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 6/9/2021 Off-Hour Fees Due
PLUMBING-Rough 6/9/2021 Off-Hour Fees Due
PLUMBING-Rough 6/9/2021 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 6/14/2021 Approved RICHARD DOCKUS
ELECTRICAL-Rough 7/9/2021 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 7/9/2021 Partial Approval RICHARD DOCKUS
PLUMBING-Rough 7/9/2021 Approved RICHARD DOCKUS
HVAC-Rough 7/15/2021 Approved ARTHUR SARGSYAN
Wood Frame 7/15/2021 Approved ARTHUR SARGSYAN
Insulation 7/19/2021 Approved DEANDRE HOFFMAN
Sewer 7/19/2021 Conditional Approval DEANDRE HOFFMAN
Sewer 7/22/2021 Approved CHRISTOPHE COCHRAN
Underground Mechanical 7/22/2021 Approved CHRISTOPHE COCHRAN
Drywall Nailing 8/16/2021 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 8/16/2021 Corrections Issued ALIZAH MAYAGOITIA
Interior/Exterior Lathing 8/20/2021 Approved CHRISTOPHER DELLEFIELD
Shower Pan 9/16/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 12/17/2021 Approved DAVID MATSON
Final 12/17/2021 Corrections Issued DAVID MATSON
Green Building Final 12/17/2021 Not Ready for Inspection DAVID MATSON
Green Building Rough 12/17/2021 Approved DAVID MATSON
SGSOV-Seismic Gas S/O Valve 12/17/2021 SGSOV Approved DAVID MATSON
Smoke Detectors 12/17/2021 Approved DAVID MATSON
Final 1/10/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 1/10/2022 Approved CHRISTOPHE COCHRAN
Final 1/12/2022 Conditional Approval JACK KARGODORIAN
Service/Power Release 1/18/2022 Not Ready for Inspection MISAEL ESPARZA
Final 2/14/2022 OK to Issue CofO JACK KARGODORIAN