1412 W SEPULVEDA ST 90732

Certificate Information: 1412 W SEPULVEDA ST 90732

Application / Permit
20014-10000-05470
Plan Check / Job No.
B20LA22847
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing recreation room attached to garage into ADU PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 3/8/2022
Issuing Office
Current Status
CofO Issued on 2/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2020 APPLICANT
Assigned to Plan Check Engineer 12/18/2020 LAWRENCE QUIRANTE
Corrections Issued 12/18/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 2/2/2021 SHANGQIN XIE
Plan Check Approved 3/1/2022 RICARDO RAMIREZ
Issued 3/8/2022 APPLICANT
Building Plans Picked Up 3/10/2022 APPLICANT
CofO in Progress 1/13/2023 ANDREW BEELI
CofO in Progress 1/13/2023 ANDREW BEELI
Permit Finaled 2/10/2023 BRUCE TODD
CofO Issued 2/10/2023 BRUCE TODD
Permit Finaled 2/10/2023 BRUCE TODD

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/26/2021 BARTON HOLMES
Address approval Cleared 1/20/2022 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 1/24/2022 ERIK BEASLEY
Sewer availability Cleared 1/24/2022 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Insulation 3/11/2022 Corrections Issued ANDREW BEELI
Drywall Nailing 3/30/2022 Approved ANDREW BEELI
Rough-Elec/Plmb/HVAC 3/30/2022 Approved ANDREW BEELI
Pre-Inspection 6/30/2022 Approved ANDREW BEELI
BUILDING-Rough-Frame 11/3/2022 Approved KEITH EDGHILL
Final 11/3/2022 Conditional Approval KEITH EDGHILL
Green Building Final 11/3/2022 Approved KEITH EDGHILL
Green Building Rough 11/3/2022 Approved KEITH EDGHILL
SGSOV-Seismic Gas S/O Valve 11/3/2022 SGSOV Approved KEITH EDGHILL
Smoke Detectors 11/3/2022 Approved KEITH EDGHILL
Final 11/7/2022 Partial Approval ANDREW BEELI
Final 1/13/2023 OK to Issue CofO ANDREW BEELI