7844 W WENTWORTH ST 91040
Certificate Information: 7844 W WENTWORTH ST 91040
- Application / Permit
- 20014-10000-05449
- Plan Check / Job No.
- B20LA22803
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 299 SF ADDITION TO THE LIVING ROOM. (N) 390 SF 2 CAR GARAGE WITH ROOF DECK. DEMO EXISTING ATTACHED GARAGE.
- Permit Issued
- Issued on 1/25/2022
- Issuing Office
- Current Status
- CofO Issued on 7/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2021 | ZAW HAN |
| Corrections Issued | 1/25/2021 | ZAW HAN |
| Quality Review Completed | 2/2/2021 | GARO TELMI |
| Applicant returned to address corrections | 4/28/2021 | ZAW HAN |
| Applicant returned to address corrections | 5/25/2021 | ZAW HAN |
| Applicant returned to address corrections | 1/3/2022 | ZAW HAN |
| Plan Check Approved | 1/4/2022 | ZAW HAN |
| Issued | 1/25/2022 | APPLICANT |
| Building Plans Picked Up | 2/16/2022 | APPLICANT |
| CofO in Progress | 6/25/2024 | WILLIAM WREN |
| Permit Finaled | 7/3/2024 | RUBEN SALAS |
| CofO Issued | 7/3/2024 | RUBEN SALAS |
| Permit Finaled | 7/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| ZA Case | Cleared | 7/29/2021 | DANIEL CORONADO |
| Low Impact Development | Cleared | 8/27/2021 | SUNG JOON WON |
| Sewer availability | Cleared | 9/8/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2021 | DAGOVERTO GUERRERO |
| Permit | Cleared | 11/24/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 11/24/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/27/2022 | No Access for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 11/4/2022 | Approved | MATTHEW NELSON |
| Deputy Reinf. Concrete | 11/8/2022 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2022 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 12/22/2022 | Corrections Issued | WILLIAM WREN |
| ELECTRICAL-Rough | 12/22/2022 | Approved | WILLIAM WREN |
| Green Building Rough | 12/22/2022 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 12/22/2022 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 12/28/2022 | Approved | WILLIAM WREN |
| Wood Frame | 12/28/2022 | Approved | WILLIAM WREN |
| Insulation | 3/7/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 3/14/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 3/29/2023 | Approved | WILLIAM WREN |
| Final | 4/12/2024 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 4/12/2024 | Corrections Issued | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 4/12/2024 | SGSOV Approved | WILLIAM WREN |
| Smoke Detectors | 4/12/2024 | Approved | WILLIAM WREN |
| Final | 5/16/2024 | No Access for Inspection | WILLIAM WREN |
| Green Building Final | 5/16/2024 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 5/16/2024 | SGSOV Approved | WILLIAM WREN |
| Final | 5/20/2024 | Corrections Issued | WILLIAM WREN |
| Final | 5/31/2024 | OK to Issue CofO | WILLIAM WREN |