2510 W AVENUE 35 90065

Certificate Information: 2510 W AVENUE 35 90065

Application / Permit
20014-10000-05443
Plan Check / Job No.
B20LA22764
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADU ADDITION TO EXISTING DETACHED GARAGE PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 2/5/2021
Issuing Office
Current Status
CofO Issued on 5/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2020 APPLICANT
Assigned to Plan Check Engineer 12/17/2020 SAMUEL GONZALEZ
Corrections Issued 12/18/2020 SAMUEL GONZALEZ
Plan Check Approved 2/3/2021 SHANGQIN XIE
Issued 2/5/2021 APPLICANT
Building Plans Picked Up 2/8/2021 APPLICANT
CofO in Progress 5/17/2022 HAMIK HARTOUNIAN
Permit Finaled 5/21/2022 DEROLD HAUFF
Permit Finaled 5/21/2022 DEROLD HAUFF
CofO Issued 5/21/2022 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 1/12/2021 NASHYA JENSEN
Address approval Cleared 1/15/2021 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 1/15/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 1/20/2021 CECILIO NAVARRO
Sewer availability Cleared 1/20/2021 CECILIO NAVARRO
Grading Pre-Inspection Cleared 1/26/2021 BARTON HOLMES

Contact Information

Contractor Cal State Construction; Lic. No.: 692212-B 632 SO LIVE OAK DR      ANAHEIM, CA 92805

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/16/2021 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 7/8/2021 Approved BENEVA JACKSON
Sewer 7/8/2021 Corrections Issued BENEVA JACKSON
ELECTRICAL-Rough 7/12/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/12/2021 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 7/12/2021 Approved HAMIK HARTOUNIAN
Sewer 7/12/2021 Conditional Approval HAMIK HARTOUNIAN
Underground Mechanical 7/12/2021 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/22/2021 Conditional Approval HAMIK HARTOUNIAN
Pre-Inspection 7/22/2021 Partial Inspection AMY COLIN
ELECTRICAL-Rough 9/17/2021 Corrections Issued BRAD BESCOS
HVAC-Rough 9/17/2021 Corrections Issued BRAD BESCOS
Insulation 9/27/2021 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 9/30/2021 Corrections Issued HAMIK HARTOUNIAN
Special/Order Compliance 9/30/2021 Partial Approval ASHLEY THOMPSON
ELECTRICAL-Rough 2/23/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/23/2022 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 2/23/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 2/23/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 2/23/2022 Partial Approval HAMIK HARTOUNIAN
Insulation 3/18/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 3/18/2022 Approved HAMIK HARTOUNIAN
Wood Frame 3/18/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 3/22/2022 Approved CHARLES BOGHOSKHAN
Gas Test 3/22/2022 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 3/22/2022 Partial Approval CHARLES BOGHOSKHAN
Interior/Exterior Lathing 4/4/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/16/2022 Approved HAMIK HARTOUNIAN
Final 5/16/2022 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 5/16/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 5/16/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 5/16/2022 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 5/16/2022 Approved HAMIK HARTOUNIAN