2510 W AVENUE 35 90065
Certificate Information: 2510 W AVENUE 35 90065
- Application / Permit
- 20014-10000-05443
- Plan Check / Job No.
- B20LA22764
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADU ADDITION TO EXISTING DETACHED GARAGE PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 2/5/2021
- Issuing Office
- Current Status
- CofO Issued on 5/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2020 | SAMUEL GONZALEZ |
| Corrections Issued | 12/18/2020 | SAMUEL GONZALEZ |
| Plan Check Approved | 2/3/2021 | SHANGQIN XIE |
| Issued | 2/5/2021 | APPLICANT |
| Building Plans Picked Up | 2/8/2021 | APPLICANT |
| CofO in Progress | 5/17/2022 | HAMIK HARTOUNIAN |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
| CofO Issued | 5/21/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/12/2021 | NASHYA JENSEN |
| Address approval | Cleared | 1/15/2021 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 1/15/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 1/20/2021 | CECILIO NAVARRO |
| Grading Pre-Inspection | Cleared | 1/26/2021 | BARTON HOLMES |
Contact Information
| Contractor | Cal State Construction; Lic. No.: 692212-B | 632 SO LIVE OAK DR ANAHEIM, CA 92805 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/16/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/8/2021 | Approved | BENEVA JACKSON |
| Sewer | 7/8/2021 | Corrections Issued | BENEVA JACKSON |
| ELECTRICAL-Rough | 7/12/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/12/2021 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/12/2021 | Approved | HAMIK HARTOUNIAN |
| Sewer | 7/12/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 7/12/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/22/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Pre-Inspection | 7/22/2021 | Partial Inspection | AMY COLIN |
| ELECTRICAL-Rough | 9/17/2021 | Corrections Issued | BRAD BESCOS |
| HVAC-Rough | 9/17/2021 | Corrections Issued | BRAD BESCOS |
| Insulation | 9/27/2021 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 9/30/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Special/Order Compliance | 9/30/2021 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 2/23/2022 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2022 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/23/2022 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/23/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/23/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 3/18/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 3/18/2022 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 3/18/2022 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 3/22/2022 | Approved | CHARLES BOGHOSKHAN |
| Gas Test | 3/22/2022 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 3/22/2022 | Partial Approval | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 4/4/2022 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/16/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 5/16/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 5/16/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 5/16/2022 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 5/16/2022 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 5/16/2022 | Approved | HAMIK HARTOUNIAN |