6208 1/2 W ORANGE ST 90048

Certificate Information: 6208 1/2 W ORANGE ST 90048

Application / Permit
20014-10000-05436
Plan Check / Job No.
B20LA22728
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
INTERIOR REMODEL AND ADDITION TO UNIT 6208 1/2 WITHIN EXISTING 4 UNIT 2 STORY APARTMENT BUILDING PER ENGINEER DEISGN
Permit Issued
Issued on 2/10/2022
Issuing Office
Current Status
CofO Corrected on 4/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 AUNG SOE
Corrections Issued 1/20/2021 AUNG SOE
Quality Review Completed 1/26/2021 HERNAN ARREOLA
Building Plans Picked Up 2/2/2021 APPLICANT
Applicant returned to address corrections 12/28/2021 AUNG SOE
Plan Check Approved 12/29/2021 AUNG SOE
Issued 2/10/2022 APPLICANT
CofO Issued-Status Void 4/3/2025 ERNESTO CORRAL
Permit Finaled-Status Void 4/3/2025 ERNESTO CORRAL
Re-Activate Permit 4/7/2025 ERNESTO CORRAL
CofO Corrected 4/7/2025 ERNESTO CORRAL
Permit Finaled 4/7/2025 ERNESTO CORRAL

Permit Application Clearance Information

"Q" conditions Cleared 3/1/2021 ANACANY HURTADO
CPC Cleared 3/1/2021 ANACANY HURTADO
ZA Case Cleared 3/1/2021 ANACANY HURTADO
Roof/Waste drainage to street Cleared 3/5/2021 CELINA MORENO
Sewer availability Cleared 3/11/2021 CELINA MORENO
Green Code Cleared 3/12/2021 AARON COSTA
Eng Process Fee Ord 176,300 Cleared 3/18/2021 CELINA MORENO
Hydrant and Access approval Cleared 5/19/2021 GILBERT URREA
Tenant Habitability Plan Cleared 8/25/2021 ISMAEL HERNANDEZ

Contact Information

Architect Hurtado,, Jesus; Lic. No.: C29969 1310 S MCDONNELL AVENUE      LOS ANGELES, CA 90022
Contractor Huezo Construction; Lic. No.: 1036747-B 28330 MAITLAND LANE      SANTA CLARITA, CA 91350
Engineer Ibrahim,, Mark Khalil; Lic. No.: S4223 3436 E LONGRIDGE DR      ORANGE, CA 92867

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 12/22/2022 Not Ready for Inspection JEROME BLACKWOOD
METHANE-Rough 12/22/2022 Not Ready for Inspection JEROME BLACKWOOD
Wood Frame 12/22/2022 Not Ready for Inspection JEROME BLACKWOOD
Green Building Rough 12/23/2022 Corrections Issued JEROME BLACKWOOD
METHANE-Rough 12/23/2022 Not Ready for Inspection JEROME BLACKWOOD
Wood Frame 12/23/2022 Not Ready for Inspection JEROME BLACKWOOD
Green Building Rough 1/5/2023 Not Ready for Inspection ALFREDO LOPEZ
METHANE-Rough 1/5/2023 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 1/5/2023 Corrections Issued ALFREDO LOPEZ
Green Building Rough 1/25/2023 Approved ALFREDO LOPEZ
Interior/Exterior Lathing 1/25/2023 Approved ALFREDO LOPEZ
METHANE-Rough 1/25/2023 Approved ALFREDO LOPEZ
Wood Frame 1/25/2023 Approved ALFREDO LOPEZ
Insulation 1/31/2023 Approved ALFREDO LOPEZ
Drywall Nailing 2/7/2023 Approved ALFREDO LOPEZ
Interior/Exterior Lathing 3/1/2023 Approved ALFREDO LOPEZ
Final 7/19/2023 Not Ready for Inspection JEROME BLACKWOOD
Footing/Foundation/Slab 7/19/2023 Approved JEROME BLACKWOOD
Green Building Final 7/19/2023 Not Ready for Inspection JEROME BLACKWOOD
METHANE-Barrier 7/19/2023 Approved JEROME BLACKWOOD
METHANE-Subgrade 7/19/2023 Approved JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 7/19/2023 SGSOV Approved JEROME BLACKWOOD
Smoke Detectors 7/19/2023 Approved JEROME BLACKWOOD
Final 8/25/2023 Not Ready for Inspection ALFREDO LOPEZ
Green Building Final 8/25/2023 Not Ready for Inspection ALFREDO LOPEZ
Final 9/25/2023 Partial Approval RAFAEL CORTES
Green Building Final 9/25/2023 Approved RAFAEL CORTES
Final 12/20/2023 Partial Approval RICARDO ROBLES
Final 6/27/2024 Not Ready for Inspection JACOB MYERS