4424 N PETIT AVE 91436
Certificate Information: 4424 N PETIT AVE 91436
- Application / Permit
- 20014-10000-05422
- Plan Check / Job No.
- B20LA22653
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL EXISTING HOUSE, RECONSTRUCT ENTRY BEDROOMS, BATH & STUDY, NEW FIREPLACE, FRONT PATIO.
- Permit Issued
- Issued on 4/5/2022
- Issuing Office
- Current Status
- CofO Issued on 7/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 12/22/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 12/29/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 1/28/2021 | APPLICANT |
| Applicant returned to address corrections | 2/18/2022 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 3/17/2022 | SERGIO GUTIERREZ |
| Plan Check Approved | 3/30/2022 | SERGIO GUTIERREZ |
| Issued | 4/5/2022 | APPLICANT |
| CofO in Progress | 6/28/2023 | JUSTIN HAWLEY |
| CofO Issued | 7/12/2023 | JOHN JANSON |
| Permit Finaled | 7/12/2023 | JOHN JANSON |
Permit Application Clearance Information
| ZA Case | Cleared | 2/18/2021 | JOE LUCKEY |
| ZA Case | Cleared | 2/18/2021 | JOE LUCKEY |
| ZA Case | Cleared | 2/18/2021 | JOE LUCKEY |
| ZA Case | Cleared | 2/18/2021 | JOE LUCKEY |
| Miscellaneous | Cleared | 7/31/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/31/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 10/3/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 1/13/2022 | MARTIN FRAGOSO |
| GPI Written Notices | Cleared | 2/18/2022 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 2/18/2022 | SERGIO GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 3/19/2022 | JOHN LIN |
Contact Information
| Contractor | Rivera Home Builders; Lic. No.: 1080029-B | 9404 BOWMAN AVENUE SOUTH GATE, CA 90280 |
| Engineer | Liu,, Wei-Chi Vicky; Lic. No.: C67158 | 1015 MILAN AVE SOUTH PASADENA, CA 91030 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/2/2022 | Conditional Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 6/20/2022 | Corrections Issued | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 6/20/2022 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 6/20/2022 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 7/7/2022 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2022 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 7/13/2022 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 9/9/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 9/16/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 9/16/2022 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 9/16/2022 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 9/16/2022 | Approved | VINCENT HANLEY |
| Insulation | 9/19/2022 | Partial Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 9/29/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 9/29/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 9/29/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 9/29/2022 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 10/21/2022 | Approved | VINCENT HANLEY |
| Shower Pan | 10/21/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 11/2/2022 | Approved | VINCENT HANLEY |
| Final | 2/28/2023 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 2/28/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/28/2023 | SGSOV Not Ready | VINCENT HANLEY |
| Smoke Detectors | 2/28/2023 | Approved | VINCENT HANLEY |
| Special/Order Compliance | 2/28/2023 | Partial Inspection | JESUS PINEDA |
| Final | 3/15/2023 | Not Ready for Inspection | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/15/2023 | SGSOV Not Ready | VINCENT HANLEY |
| Final | 6/12/2023 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Approved | VINCENT HANLEY |
| Final | 6/27/2023 | OK to Issue CofO | JUSTIN HAWLEY |